CPI/ SPI Trend by Project

The cost performance index (CPI) and schedule performance index (SPI) values are calculated using the Planned Value, Earned Value, and Actual Value of the selected project; for the specified period.

To view the CPI/ SPI Trend by Project metric, go to Overall Project Performance > CPI (or) SPI > Earned Value by Project > CPI\ SPI Trend.

[...]