| | Using progress payment requestsProgress payments
requests are generated for the costs incurred when working on a contract with
the business partner. Progress payment invoices are sent to the customer based
on an agreed billing cycle and settled using the installment or delivery based
invoices. The progress payment request process is used to create a US specific
Standard Form 1443 invoice. Note - This process can be used only if the required parameter is
selected.
- Progress Payments are only applicable for fixed price
contracts.
- The holdback functionality is not applicable for Progress
Payment Requests.
- Progress Payment Requests are not included in the Revenue
Analysis.
To set-up progress payment requests data, you
must: - Specify the revenue code in the General Project Parameters (tppdm0100s000) session.
- Select the Progress Payment Requests check box in the Contract Parameters (tpctm0100m000) session.
- Select the Small Business check box to ensure the business
entity is a small business, and to print the value on the Standard Form 1443.
The check box is enabled only if the Progress Payment Requests check box is
selected.
To define a progress payment request You can define the progress payment requests details on the Progress Payment Requests tab in the Contract (tpctm1600m000) session: - Specify the contract.
- Select the Progress Payment check box to create the progress
payment request for the contract.
- Specify the progress payment percentage. The percentage of
cost for a contract that is considered for invoicing. The commonly used
progress payment percentages range between 75-80%.
- Specify the progress liquidation percentage used for
calculating the amount to settle the progress payment invoices.
- Specify the invoicing method.
- Specify the payment terms.
- Select the Billable Cost Report check box to print an additional
report while creating the invoice.
- Create a contract line(s). For more information, refer to Contract lines data setup. Infor LN defaults
the progress payment data defined for the contract, on the Progress Payment
tab.
To create a progress payment request Note - You can review the progress payment requests data in the Progress Payment Requests (tppin0170m000) session.
- You can review the settled progress payment requests data
in the Settled Progress Payment Requests (tppin0571m000) session.
Invoicing You must use the relevant invoicing method and payment term
specified for the contract line. Invoicing may differ based on: - Progress Payments invoices settled at agreed intervals, based
on the progress of the contract.
- Progress payment invoices including the advance
payments.
- Progress payment invoices settled with installments/delivery
based invoices.
Note - When Progress Payment Requests are settled using
Installments or Deliverables, a reverse entry is generated in
Financials.
- Infor LN registers revenues for the requests using the revenue of the
type Progress Payment Request, in the Revenue Transactions (tpppc3505m000) session.
- When generating the balances for interim results, Progress
Payment Requests are included to calculate the Billed to Customer
amount.
- Infor LN also allows the user to print a US specific invoice, Standard Form
1443 (SF1443) Contractors's Request for Progress Payment. To print both these
standard forms, the Infor Operational Reporting functionality is required. The
SF form 1443 must also specify the unsettled advance amount.
- Progress payment requests are posted using the existing
Integration Document Type Project Revenue/Revenue Analysis.
| |