| How LN calculates the performedIn performance measurement and monitoring, LN calculates the performed in different ways,
depending on a number of settings: Costs have been registered on an extension for which, in
the Extension (tpptc0110s000) session, both of the following applies: In this case, LN calculates the
performed as follows: Performed = Budgeted Amount * Progress If the project is a cost-plus project, the costs cannot be
registered using an extension. Interim results are not determined and the
progress registration states that production is not finished. In this case, LN calculates the
performed: Performed = Costs Posted to History Costs have been
registered on an extension for which, in the Extension (tpptc0110s000) session, the Extension Type is set to Quantities to be Settled. For a part of the project (such as a number of material
lines for a specific element) for which the progress data indicates that
production is finished, or production is greater than 100 percent, LN calculates the
performed as follows: Performed = Budget Amt ((Budget Qty * Progress) - Budget Qty) * Sales Price in Control Budget Note:
The performed material costs are increased by the inventory as stated in the
progress data, multiplied by the cost price for the material. Otherwise, LN calculates the performed as follows: Performed = Budgeted Amount * Progress Note:
The performed material costs are increased by the inventory as stated in the
progress data, multiplied by the cost price for the material.
| |