To use a control budgetThe control budget is a derived budget based on the project budget and surcharges. Create this budget with the Generate Control Data (tpptc1230m000) session. You can use the control budget as a frozen budget for the following operations:
The type of control budget generated is initially determined by the Control by field in the Projects (tppdm6100m000) session.
Element budget If the project budget is based on elements, the generated control budget includes only elements for which the Cost Control check box is selected in the Elements (tpptc1100m000) session. If this check box is cleared, the budget lines of the element are aggregated to the next higher level element for which the check box is selected. If the project budget is based on elements with an activity budget control type the control budget is a combination of two budgets: the leading element control budget and the activity control budget. If you run the Generate Control Data (tpptc1230m000) session the two budgets are created and the element budget is copied to the activity budget. In this activity budget you can only change the scheduling data. (You can also copy the element budget to the related activities in the Copy Element Budget to Activity Budget (tpptc1240m000) session). Budget lines related to elements for which the Cost Control check box is cleared are aggregated to the next higher level parent element for which the Cost Control check box is selected. Duplicate budget lines are compressed by element/cost component and extension in the control budget. Any surcharges are computed and the calculated amounts are stored in the control budget. Activity budget If the project budget is based on activities, the generated control budget includes all activities that are:
| |||