Work Center Utilization by Day (tisfc1506m000)

Use this session to display an overview of capacity utilization of a work center for one day. You can see, for each order, the time and quantity that it is planned.

Reports

By selecting Print from the File menu, you can start the following sessions:

  • Print Work Center Utilization by Day (tisfc1403m000).
  • Print Shared Work Center Utilization by Day (tisfc1406m000), if the work center is a secondary work center that is linked to a primary work center and the secondary work center is in the same logistic company as the primary work center.

 

Work Center

The work center for which you want to see a summary of what capacity requirements are planned for that day.

To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.

Description

The work center for which you want to see a summary of what capacity requirements are planned for that day.

To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.

Normal Capacity

The average capacity of a machine or work center that is used as the basis for the capacity utilization.

Production Date

The day for which you want to see a summary of what capacity requirements are planned.

Available Cap

The available capacity (hours) of the employee working at the work center for the day in question.

Start Time

The start of the period for which you want to see what capacity has been planned.

Production Order

The code of the planned production order.

Item

The item produced in the operation.

Routing

The sequence of operations required to manufacture an item.

For each operation, the task, machine, and work center are specified, as well as information about setup time and cycle time.

Note

If no routing is displayed, there are no estimated production costs defined for the production order.

Operation

The code of the operation planned for the work center.

Machine

The machine with which the operation is carried out.

Quantity Planned

The quantity of items you plan to produce in this operation on this date, including items lost to scrap and low yield.

Man Hours

The man hours needed to carry out the operation

Physical Location

The location where the order is processed.

SFC Order Group

The group of orders to which the order belongs.

Related topics

Machine Hours

The machine hours needed to carry out the operation

Normal Capacity

The average capacity of a machine or work center that is used as the basis for the capacity utilization.

Available Cap

The available capacity (hours) of the machine working at the work center for the day in question.

 

Production Planning
Build Utilization

Starts the Build Utilization (tisfc0201m000) in which you can update the plans from the Enterprise Planning module. All the utilization data is deleted and is regenerated using the production quantity and date data in the Production Planning (tisfc0110m000) session. This cannot be done for line work centers.

You must select Automatic in the Update Method Day Utilization field and Automatic in the Update Method Week Utilization field in the Shop Floor Control Parameters (tisfc0100s000) session before you can use this option.