| Order Block Planning by Plan Board (tisfc1152m000)To start this session, first start the Select Data for Order Sequencing Plan Board (tisfc1151m000) session. Note This graphical planning board is available only in the WebTop
client. How to use the plan board When you start the plan board, the plan board displays one bar
for each machine and each order-block period within the selection
range. To change the view The following table describes how you can change what
information the plan board displays. In order
to... | Do this... | View all the order blocks of a machine and order-block
period without changing the time scale. | Click on the arrow point in the Machine / Order Block Period / Block Sequence Number column. | Zoom in
on a machine and order-block period and view all related order
blocks. | Double-click the combination of machine and order block period
in the Machine / Order Block Period / Block Sequence Number column. | Display ToolTips with additional details. | Point to the codes of the machine and order block periods in the Machine / Order Block Period / Block Sequence Number column or point to the graphical
bars. | Start the Production Orders by Block (tisfc0152m000) session. | Double-click an
order-block. | View the order blocks in the sequence as the
order blocks were originally generated. | On the Specific menu, click View by Original Block Number In this view, you cannot modify the sequence. | View the order blocks in the current sequence. | On the Specific menu, click View by Block Sequence Number In this view, you can modify the sequence. |
To manipulate order blocks The following table describes how you can manipulate the
order blocks in the plan board. In order
to... | Do this... | Modify the start date
and end date of an order block. | Drag the order block to an earlier or later date. Note: This action does not adjust the start dates
and end dates of the other order blocks. | Reschedule the order blocks that come after the
order block you just moved to an earlier or later date, without
changing the relative order of the order blocks. | - Select the order block where the rescheduling
action must start.
- On the Specific menu, click Reschedule Order Blocks.
The order blocks before the selected order block are
left unchanged. The currently selected order block's start time is the starting
point of the rescheduling action. LN also reschedules the order blocks after the
selected order block. LN takes the applicable calendar into account. | Reschedule all order blocks, without
changing the relative order of the order blocks. | - Make sure that none of the order blocks is
selected.
- On the Specific menu, click Reschedule Order Blocks.
The start date of the order block period is the
starting point of the rescheduling action. LN reschedules all the
order blocks. LN takes the applicable calendar into account. | Modify the relative order (sequence) of the
order blocks. | - Drag the order blocks to an earlier or later
position in such a way that the start times of the order blocks correspond with
the desired sequence.
- On the Specific menu, click Recalculate Block Sequence Numbers and Reschedule.
|
None of the actions you execute in this plan board have any
effect on the actual planned orders in the Production Orders (tisfc0501m000) session and the Production Planning (tisfc0110m000) session, until you update the standard planning data. To update the standard planning data To update the standard planning data for all order blocks
that belong to a machine and order block period, take the following
steps: - Select the bar for the machine and order block
period.
- On the Specific menu, click Update Standard Planning.
If you click Update Standard Planning after you selected the bar for a specific order
block, LN updates the actual planning data for that order block and all subsequent order
blocks that belong to the same machine and order block period. Sequence of production orders and operations LN schedules the production orders in an order block according to the value of the
originally planned finish date of the relevant operation. If you reschedule an operation, LN reschedules the
other operations of the same production order according to the setting of the
following parameters in the Default Production Order Data (tisfc0102m000) session: | |