Production Order Distribution (tisfc0105m000)

Use this session to display and edit the order quantities of the effectivity units for a production order. The ordered end item quantity can be distributed over one or more effectivity units.

It is mandatory to have a distribution with project pegs if the end item of the production order is mandatory project pegged.

Note

If the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session, and if you manually change the peg distribution, a window is displayed in which you must specify a reason code.

 

Distribution
Production Order

An order to produce a specified quantity of an item on a specified delivery date.

Order Status

The order status of the production order.

Allowed values

Order Status

Item

The item produced by the production order.

Warehouse

The warehouse in which the item is stored after completion.

WMS Controlled

If this check box is selected, you defined in the Warehouses (tcmcs0503m000) session that an integration with a Warehouse Management System (WMS) exists.

Standard Configuration

If this check box is selected, all effectivity units that are listed in this session concern an item that has a standard configuration.

Line

The number of the distribution line.

Project

An endeavour with a special objective to be met within the prescribed time and money limitations and that has been assigned for definition or execution.

Element
Activity
Project Peg Origin

The origin of the project peg for the production order.

Allowed values

Project Peg Origin

Effectivity Unit

A reference number, for example a sales order line or a project deliverable line, that is used to model deviations for a unit effective item.

Zero (0) indicates the standard configuration.

Quantity Ordered

The quantity ordered for the Distribution Line.

The total quantity ordered on the distribution lines makes up the quantity on the header. When the quantity ordered on the distribution lines is changed the total on the header is updated.

Note

You can reduce the order quantity for released orders, for example, from 10 to 7 pieces. However, you cannot change the order quantity to a value less than the quantity that is reported as complete on an operation. If you want to enter a ordered quantity that is less than the quantity on an operation, you must reduce the quantity on the operation first. To do this, you must take the following into account:

  • If the operation status is Completed, you must reset the operation status to Active.
  • If a count point is used on the operation, you must first remove the count point before you can complete the order with a lower quantity.
Quantity Reported on Last Operation

The number of items for the specific effectivity unit that is reported as complete on the last operation but that have not been delivered to the warehouse yet.

To Deliver

The quantity to be delivered to the warehouse for the Distribution Line.

You can modify the value of this field in the Production Order Distribution (tisfc0105m000) details session, if the Order Status is greater than or equal to Released.

Delivered

The quantity already delivered for the Distribution Line.

Rejected

The quantity of the production order that was rejected during the production process.

Note

Once a quantity is rejected, it can either be Quarantined or scrapped.

Quantity Scrapped

The quantity that is scrapped. These end items cannot be sent to quarantine for possible reworking.

Related topics

Quarantined

The quantity that is quarantined.

Lot Code

The lot to which the completed products belong.

You can modify the value of this field in the Production Order Distribution (tisfc0105m000) details session, if the Order Status is greater than or equal to Released.

Note

The Lot Code can not be manually modified if Project Pegging is selected on company level.

Planning Group

A planning group is used for segregation in planning of project specific demand and supply. Commingling rules and cost transfer rules can be defined on planning group level to control supply planning behavior of project pegged items within the planning group as well as with other planning groups.

Note

A project can only be assigned to one planning group.

Details
Line
Quantity Initial

The order quantity for the effectivity unit at the time the production order was released.

Quantity On Order

The number of items for the specific effectivity unit on the production order.

Backflush to Do

The quantity to be issued by backflushing for the effectivity unit.

Backflushed

The quantity already issued by backflushing for the effectivity unit.

Configuration
Item

The item produced by the production order.

Unit Series

A range of sequence numbers that is linked to an end item and represents one or more effectivity units. An effectivity series consists of a unit series code, a from-sequence number, and a to-sequence number. An effectivity series is identified by the unit series code and the from-sequence number. You can link one or more effectivity units to a combination of end item, unit series code, and from-sequence number.

An effectivity series is identified by the unit series code and the from-sequence number.

You can link one or more effectivity units to a combination of end item, unit series code, and from-sequence number.

Unit Sequence

The sequence number of the effectivity unit.

 

Pegging - Upstream

Click Pegging - Downstream to start the GBF browser in which you can view the production order's supply orders, that is, the preceding production orders and/or purchase orders.

Click Pegging - Downstream to view the production order's demand orders, that is, the successive production orders and/or sales orders.

You can only start pegging if the following is true:

For more information, refer to Pegging for planned orders.

Pegging - Downstream

Click Pegging - Downstream to start the GBF browser in which you can view the production order's supply orders, that is, the preceding production orders and/or purchase orders.

Click Pegging - Downstream to view the production order's demand orders, that is, the successive production orders and/or sales orders.

You can only start pegging if the following is true:

For more information, refer to Pegging for planned orders.