| Update Method of Production OrderRecalculate The quantities and the dates and times are recalculated, but the
production order is not set up as a completely reprocessed new production
order. Regenerate The production order is completely regenerated, which means that
the data about materials and routing operations is retrieved from the Bill of Material and the Routing modules. Any
material that was manually added to the estimated material costs will be
discarded. If the BOM and routing were changed since the production order was
created, these changes are incorporated in the production order. No Action
| |