Split

  • By Operation Only

    All actual material costs are aggregated to the operation level before transfer. This lowers the amount of transactions.

    Note

    If this parameter is selected, price variance per material cannot be calculated properly.

  • By Operation and Material Position

    All actual material costs are transferred separately.

    Note

    If this parameter is selected, the amount of transactions logged will increase, especially when an operation requires many material components.