BOM Line - Material-Routing Relationships (tibom0140m000)

Use this session to define and maintain material-routing relationships for a specific main item.

 

Main Item

The main item for which the BOM is maintained.

Description

The description or name of the code.

Position

The component's BOM position number.

Slash Character

The BOM sequence number is a subdivision of the component item's BOM position number. If you create orders for a manufactured item, only the material with the lowest valid sequence number is taken into account. A material sequence number can be (in)valid due to effectivity dates or unit effectivity settings.

Item

The component item of the manufactured item.

Routing

A routing that is used to produce the main item. You can define one or more routings for an item in the Item - Routings (tirou1101m000) session.

Operation

The routing operation at which the BOM line's item must be issued to the shop floor.

More than one routing can be available to produce an item. The operation at which a material is issued can differ for the various routings.