| Implemented software component checksLN performs the following checks when you select the
various check boxes in the Implemented Software Components (tccom0100s000) session. - If Manufacturing is not installed, you cannot select the check boxes for
any Manufacturing modules or the engineering revisions concept.
- You cannot use the Assembly Control module and the Tools Requirement Planning modules of Manufacturing together. Therefore, if you
select the Assembly Control (ASC) check box, you
cannot select the Tool Requirements Planning (TRP) check box,
and vice versa.
- If Supply Chain Scheduler is
implemented, you cannot select the Repetitive Manufacturing (RPT) check box.
- To use Supply Chain Planning or order Promising Server, you must implement Enterprise Planning.
- To use Supply Chain Planning, you must select the Enterprise Planning (CP) check box. In
addition, the Move Allocation to Shop Floor Warehouse field in the Shop Floor Control Parameters (tisfc0100s000) session must be set to At Generation.
- If you use Supply Chain Scheduler, the Automatic Update Production Order Start Date check box in the Shop Floor Control Parameters (tisfc0100s000) session must be selected.
- If Manufacturing is not implemented, you cannot use the Supply Chain Execution Manager.
-
If you use Supply Chain Execution Manager, the following parameters in the Shop Floor Control Parameters (tisfc0100s000) session must have specific values:
| |