Efficiency factors

LN uses efficiency factors to take into account variable daily capacity for lead-time calculation.

Various reasons can exist for variability in daily capacity: reduction of work force in the holiday season, or hiring extra work force in busy periods means that there is more or less plan time available on a specific day.

The default value of the efficiency factor is 1.0.

To define the efficiency factor

You can define efficiency factors when you set up a calendar in the Calendars and Periods module of Common.

The following table shows several ways to define efficiency factors:

To do this...Use this session...
To define a default efficiency factor for a working hours typeWorking Hours Types (tcccp0103m000)
To define the default efficiency factor for a particular day of the weekStandard Calendar (tcccp0140m000)
To define an efficiency factor at recurring datesCalendar Recurrences (tcccp0144m000)
To overwrite a default efficiency factor on a particular dateCalendar Working Hours (tcccp0120m000)
To change the efficiency factors for multiple calendars and availability typesUpdate Efficiency Factor and Capacity (tcccp0225m000)

 

After you change the efficiency factor, you must update the calendar. Use one of the following methods:

  • Run the Update Calendars (tcccp0226m000) session.
  • In the Calendar Working Hours (tcccp0120m000) session, click Update Calendar.

After you changed the efficiency factor, update the calendar by using the Update Calendars (tcccp0226m000) session, or by clicking Update Calendar in the Calendar Working Hours (tcccp0120m000) session.

To view the effective availability factor on particular dates, use the Calendar Working Hours (tcccp0120m000) session. Remember to update the calendar.

To use efficiency factors

LN uses efficiency factors for the following purposes:

  • To take into account that resources can sometimes work more efficient than the average. For example, if a particular employee works harder in the morning than in the afternoon, you can enter an efficiency factor of 1.1 for the calendar line with time interval 09:00 - 12:00.
  • To take into account that, if you hire additional resources to perform the work, the lead time of operations shortens.
Note

Do not confuse efficiency factors with capacity percentages.

  • Efficiency factors affect the lead-time calculation for which the corresponding calendar is used. In other words, these factors influence the speed at which the work is carried out.
  • Capacity percentages provide information about the utilization rate of a resource.