Freight order date modificationThe shipment of goods to customers or warehouses can be delayed due to stock shortages, transport capacity issues or problems at the receiving side. When freight orders are delayed, the planned load/unload dates and the tolerance dates are no longer applicable. It is rare that all the lines in a freight order are delayed. Most often, some freight order lines are successfully shipped and others are delayed, due to inventory shortages. To process these freight orders or lines at a later stage, you can adjust the following:
When you adjust the dates ( Planned Load Date or Planned Unload Date) and tolerances ( Earliest Load Date and Earliest Unload Date; Latest Load Date and Latest Unload Date), LN planning engine retrieves the affected order lines and includes the order lines in a new freight plan that is scheduled to be executed at a later date. To maintain dates or tolerances on individual freight order
lines To view the list of delayed freight order lines, open the Freight Order Lines (fmfoc2101m000) or the Freight Order Lines (fmfoc2101m100) session. Click appropriate > View > View Overdue Lines Only. All the delayed freight order lines with the following status are displayed:
You can modify the planned load/unload dates and/or the tolerance dates only for order lines with the Expected, Planned, and Actual status. When you modify the Planned Load Date, the tolerance dates are calculated automatically, based on the original tolerance agreements. To calculate the Planned Unload Date, click Calculate. The related tolerance dates are calculated automatically. When you modify the Planned Unload Date, the tolerance dates are calculated automatically, based on the original tolerance agreements. To calculate the Planned Load Date, click Calculate. The related tolerance dates are calculated automatically. Note If the dates on a freight order line are moved to a future date and afterwards the tolerance dates on the order header are modified, the date adjustment on the order line holds and is not impacted by the tolerance change on the order header. To maintain tolerances on individual freight order For a freight order, you can only modify the Tolerance dates ( Earliest Load Date and Earliest Unload Date; Latest Load Date and Latest Unload Date) on the header. The tolerance dates of the freight order lines with the Expected, Planned, and Actual status are modified. Collective change of dates or tolerances on freight
orders You can modify the planned load/unload dates and tolerance dates for a range of freight orders and order lines using the Change Planned Load/Unload Date (fmfoc2201m000) session. The session can be started from the appropriate menu of the following sessions: You can use the following sessions:
Operational Procedure for the transport
planner
| |||