To replan changed Actual freight orders

The Update Actual Load Data field in the Freight Planning Parameters (fmlbd0100m000) session enables you to specify how Freight deals with load building after changes are made in freight orders that have the Actual status.

In the Update Actual Load Data field, the following settings are available:

  • Not Allowed

    You cannot replan Actual freight orders or order lines, because users cannot change freight orders, freight order lines, or originating orders of freight order lines that are Actual. If a user attempts to make a change, an error message appears.

  • Manual Replanning

    Freight order lines that have been changed can be replanned manually. If a freight order line is changed, LN inserts the changed freight order line in the Freight Order Lines to Be Replanned (fmlbd0120m000) session. In the Freight Order Lines to Be Replanned (fmlbd0120m000) session, you can select the changed freight order line and access the Generate Plan (fmlbd0280m000) session from the appropriate menu.

    A freight order can be changed in the Freight Order Lines (fmfoc2101m000) session. A freight order line is also changed if the originating order line is changed. If the originating order header is changed in such a way that it affects the originating order line and the related freight order line, the freight order line is also changed. This is the case if, for example, the planned delivery date on the originating order header is changed.

    After a freight order line is changed, any shipment lines related to the freight order line are deleted, and the freight order line is inserted in the Freight Order Lines to Be Replanned (fmlbd0120m000) session. The changed freight order line receives the Planned status again, and the user can replan the order line.

  • Automatic Replanning

    If an order is changed that is already part of an actual plan, the related shipment lines are removed from the plan. The changed freight order line is replanned automatically and does not appear in the Freight Order Lines to Be Replanned (fmlbd0120m000) session. If you cannot replan, you cannot change the order.

Note
  • A changed freight order line can be inserted in a different or a new freight order. As a result, the freight order number and the position number can also have changed.