Resource Order Plan - Find (cprrp0531m000)

Use this session to specify for which scenario and for which resource LN must display the capacity requirements. In addition, you must specify for which and how many time intervals LN must display capacity data.

 

Scenario

Specify the scenario for which LN must display resource capacity data.

Plan Level

Specify the plan level for which LN must display resource capacity data.

Plan level 0 is not allowed.

Resource

Specify the resource for which LN must display the capacity utilization.

Critical Capacity Type

The Critical Capacity Type that will be displayed on the resource order plan. See Critical Capacity Type.

Shown Capacity Type
Start Date

Define the start date of the time bucket for which LN must display the capacity utilization for the specified resource.

Period Length

Select the length of the time bucket for which LN must display the capacity utilization for the specified resource. Select one of the following values:

  • 1 Day: LN displays the capacity usage for the number of days specified in the Number of Periods field.
  • 7 Days: LN displays the capacity usage for the number of weeks specified in the Number of Periods field.
  • 14 Days: LN displays the capacity usage for the number of biweekly periods specified in the Number of Periods field.
  • 28 Days: : LN displays the capacity usage for the number of four-weekly periods specified in the Number of Periods field.
  • Detail: LN displays al the orders and the resource capacity they require for the number of days specified in the Number of Periods field.

If you defined a date in the Start Date field, and specified the length of the period, LN checks if the specified period does not exceed the:

If one of these dates is exceeded, LN gives a warning.

Number of Periods

Specify the number of periods for which LN must display capacity utilization data of the specified resource. These periods have the length you defined in the Period Length field. The value 0 is not allowed.

LN displays a warning if the number of periods exceeds the:

Hide 'Empty' Periods

If this check box is selected, LN only displays the periods in which orders exist that require capacity of the specified resource.