Convert Master Plan to Planned Orders (cprmp2240m000)

Use this session to convert a plan item's production plan and/or purchase plan to planned orders.

 

Scenario

Specify the scenario for which LN must move item master plans to planned orders.

If a scenario's plan status is Closed, you can no longer modify the data that is related to this scenario.

Plan Level

Define the plan level of the plan items of which LN must move the purchase plan and/or the production plan to planned orders.

From Plan Item

Specify the first of a range of plan items of which LN must move the purchase plan and/or the production plan to planned orders.

To Plan Item

Specify the last of a range of plan items of which LN must move the purchase plan and/or the production plan to planned orders.

Planner

Specify the first of a range of planners that LN must use as a criterion to select plan items of which it must move purchase plans or production plans to planned orders.

Set the Planner selection range to maximum, if you do not want to constrain your item selection by selecting planners.

Planner

Specify the last of a range of planners that LN must use as a criterion to select plan items of which it must move purchase plans or production plans to planned orders.

Set the Planner selection range to maximum, if you do not want to constrain your item selection by selecting planners.

Period

Specify the first of a range of plan periods for which LN must move production plans or purchase plans to planned orders.

Period

Specify the last of a range of plan periods for which LN must move production plans or purchase plans to planned orders.

Generate Planned Production Orders

If this check box is selected, LN converts the production plan for the selected plan periods to planned production orders.

Only in Order Horizon

If this check box is selected, LN only generates planned orders within the order horizon.

If this check box is cleared, LN also generates planned orders beyond the order horizon.

Generate Planned Purchase Orders

If this check box is selected, LN converts the purchase plan for the selected plan periods to planned purchase orders.

Note

LN only moves the purchase plan to planned purchase orders, and not to purchase schedule quantities.

Order Status to Firm-Planned

If this check box is selected, the planned orders that LN automatically generated get the Firm Planned order status. This prevents LN from removing these orders during a normal order planning run.

If this check box is cleared, the generated planned orders get the Planned order status.

Error Report

If this check box is selected, LN creates a report that contains the exception messages and error messages that are generated during the process of generating planned orders.

Move in Multi-site

If this check box is selected, LN also moves master plans to planned orders in each plan site that falls in the specified range of sites.

The following conditions apply:

  • This option is only available if the specified scenario is a central multisite scenario.
  • LN only takes into account the plan sites that are linked to the central multisite scenario involved.
  • In each plan site involved, LN only takes into account the master plans that exist in the plan site's local scenario.
Note
  • You can designate a scenario as a central multisite scenario in the Scenarios (cprpd4100m000) session.
  • You can specify plan sites for a central multisite scenario (and a local scenario for each plan site) in the Scenario - Sites (cprpd4140m000) session.

Related topics

From

The first site in the range of sites for which you want LN to move master plans to planned orders.

To

The last site in the range of sites for which you want LN to move master plans to planned orders.

Update Master Plans

If this check box is selected, LN automatically updates the item master plan and the resource master plan after LN moved the purchase plan and/or the production plan to planned orders.

Period

The end date of the specified plan period.

Period

The end date of the specified plan period.

 

Convert

Starts the specified action.