Forecast Consumption without an Item Master PlanIf an item has no item master plan, the only available type of demand forecast is special demand. You can enter special demand for an item or item/channel combination in the Special Demand by Item (cpdsp2100m000) session. LN automatically applies forecast consumption during an order simulation. In the Item Order Plan (cprrp0520m000) session and the Special Demand by Item (cpdsp2100m000) session, you can also manually perform forecast consumption. Forecast-consumption procedure The dates of the forecast demand and the actual demand that consumes it do not have to match exactly. A particular instance of actual demand can also consume forecast demand from an earlier moment, or forecast demand from a later moment. This depends on the values of the following fields in the Scenarios (cprpd4100m000) session:
Example Suppose that there is an instance of actual demand on date (and time) P. The starting moment for consumption (B) is P minus the value of the Backward Forecast Consumption field. The end moment for consumption (Y) is P plus the value of the Forward Forecast Consumption field. The starting moment (B) is rounded to the start of the day (time 00:00:00). The end moment (Y) is rounded to the end of the day. If the Backward Forecast Consumption and the Forward Forecast Consumption field are zero days, LN consumes the special demand of a single day. The consumption proceeds as follows:
This consumption procedure takes place in two phases. Phase 1 In this step, only customer demand that falls in a channel is considered. This demand is used to consume the special demand defined for a particular item/channel combination. Phase 2 In this step, all remaining actual demand is considered:
| |||