To maintain a resource master planThis topic explains how you can generate, review, update, or delete resource master plans. How to generate a resource master plan How to view and update a resource master
plan In the Resource Master Plan (cprmp3501m000) session, you can review the resource master plan. The resource master plan contains capacity use from various sources. For capacity planning, Enterprise Planning uses the value that you specified in the Basic Number of Machines field in the Resource (cprpd2100m000) session. If you did not specify a value in this field, for capacity planning, Enterprise Planning then uses the value that you specified in the Basic Number of Operators field of the Resource (cprpd2100m000) session. Note Enterprise Planning only records the capacity use of SFC orders if the Update Method Day Utilization field in the Shop Floor Control Parameters (tisfc0100s000) session is set to Automatic or Manual. You can update the resource master plan by choosing the Generate command on the appropriate menu. If a resource's calendar is changed, you can use the Rebuild Resource Planning (cprmp3200m000) session to regenerate the resource planning. How to delete a resource master plan You can delete a resource master plan, or a range of resource master plans, in the Delete Master Plan (cprmp2210m000) session.
| |||