Net-change date before time fenceIf LN detects changes that influence planned orders, for example, a changed BOM, LN sets the net-change date to the date of these changes. A zero net-change date indicates that nothing has changed since the last simulation. After simulating an item, LN resets the net-change date to zero. If the net-change date lies before the time-fence date, two problems arise:
Resetting the net-change date If you run an order simulation by means of the Generate Order Planning (cprrp1210m000) session or the Generate Order Planning (Item) (cprrp1220m000) session, the Reset Net Change in Time Fence check box determines if LN resets a net-change date that falls within the time fence. Note If the Generate Within Time Fence check box is selected, LN always resets the net-change date. In this case, the Reset Net Change in Time Fence check box is unavailable. If you clear the Reset Net Change in Time Fence check box, LN does not reset a net-change date that falls within the time fence. This setting has the following consequences:
If you select the Reset Net Change in Time Fence check box, LN always resets the net-change date. This setting has the following consequences:
Note In master planning, a net-change date that falls before the time fence is always reset during a simulation.
| |||