Physical Breakdown Change Lines (tscfg2141m000)

Use this session to view the changes in the physical breakdown structure of a parent item and a component. This session can be accessed only as a satellite session.

Note
  • You can view this session only if the Physical Breakdown Changes check box is selected in the Configuration Management Parameters (tscfg0100m000) session.
  • You cannot delete the change line that has the Copied from PBS check box selected.
  • You cannot add, modify or delete the line if the header Status is set to Closed.
  • You cannot modify or delete the line if the line Status is set to Breakdown Updated.
  • You can delete the line only if the Source of Change is set to Manual.
  • For each Source of Change, only one line can exist.
  • You cannot modify the line if the Source of Change is set to Service Order, Maintenance Sales Order or Work Order.
  • You cannot modify the line, if the Status for the item related to the change line is set to To be Installed or To be Removed in the Physical Breakdowns (tscfg2110m000) session.

 

Parent Item

The code of the parent item. The components of this item are changed.

Note

This value is defaulted from the Physical Breakdown Changes (tscfg2140m000) session.

Parent Serial Number

The serial number of the parent item. The components of this item are changed.

Note

This value is defaulted from the Physical Breakdown Changes (tscfg2140m000) session.

Contract Change Number

The number that identifies the change in the physical breakdown structure of the Parent Item.

Note

This value is defaulted from the Physical Breakdown Changes (tscfg2140m000) session.

Position

The position number of the component in the physical breakdown structure.

Note

This field can be modified only when you create the PB change line manually. When you modify the value, ERP LN checks for an existing physical breakdown with the same position number in the Physical Breakdowns (tscfg2110m000) session. You cannot use the position number for which a physical breakdown is available.

Old Item

The code of the old component in the physical breakdown structure.

Old Serial Number

The serial number of the old component in the physical breakdown structure.

Old Item Description

The description or name of the code.

Source of Change

The source of the change.

Allowed values

Source of Change

Note
  • This value is determined by the status of the related order and is set to Before Order or Manual, if change line is created manually.
  • By default, this value is set to Manual if an order is not related to a change line.
Action

The action that is performed on the component line.

Allowed values

Action

Note
  • If the New Quantity of the item is set to zero, ERP LN defaults this field to Remove.
  • This field cannot be set to Remove or Replace, for a newly created line.
Description

The description or name of the code.

New Item

The code of the new parent item

Note
  • This field is disabled if the header Status is set to Closed.
  • This field is not applicable when the Action is set to Keep or Remove.
  • You cannot modify this value if the Source of Change is set to:
    • Service Order
    • Maintenance Sales Order
    • Work Order
New Serial Number

The serial number of the new parent item

Note
  • This field is disabled if the header Status is set to Closed.
  • This field is not applicable when the Action is set to Keep or Remove.
  • You cannot modify this value if the Source of Change is set to:
    • Service Order
    • Maintenance Sales Order
    • Work Order
  • To create a change in the physical breakdown structure, the serialized item Status in the Serialized Items (tscfg2100m000) session must not be set to:
    • Startup
    • To be Recycled
    • Superseded
    • Removed
  • You cannot create a physical breakdown structure for a new serialized item.
  • You cannot use the Old Item (serialized) as New Item (serialized) if the Action is set to Replace.
  • You cannot modify this value if the Source of Change is set to:
    • Service Order
    • Maintenance Sales Order
    • Work Order
New Item Description

The description or name of the code.

Old Quantity

The old quantity of the child item in the physical breakdown structure.

Note
  • This value is not applicable if the Action is set to Install.
  • This value is defaulted from the Quantity defined in the Physical Breakdowns (tscfg2110m000) session.
New Quantity

The new quantity of the child item in the physical breakdown structure.

Note
  • This field is disabled if the header Status is set to Closed.
  • This value is mandatory and must be positive when the New Item and New Serial Number are specified.
  • You cannot modify this value if the Source of Change is set to:
    • Service Order
    • Maintenance Sales Order
    • Work Order
Status

The status of the change line.

Allowed values

Change Line Status

Workflow Status

The status that is applicable for the business object requires authorization using ION Workflow.

When you perform a change that requires authorization, a checked-out version is created for the business object. These changes are effective only after the approval/check-in.

  • Checked-out and checked-in objects are displayed in the Checked-out Objects (ttocm9599m000) session.
  • From the appropriate menu of this session, select Workflow and then select the required action for the business object.

Allowed values

If the business object is checked out, this field is set to Object status.

If the business object is checked in, this field is set to Approval status.

Regardless of the object being checked in or checked out, if a description is specified for the object type in the Workflow Information Fields (ttocm0106m000) session (which is displayed as a tab in the Object Types (ttocm0102m000) session), this field always displays the value of the appropriate Description field.

Note

For more information on setting up and using ION Workflow for business objects in LN, refer to the Infor LN Content Guide for Infor ION guide at Infor Xtreme.

Lot

The lot number of the new item in the physical breakdown structure.

Note
  • This field is disabled if the header Status is set to Closed.
  • This value is defaulted from the Lot field in the Serialized Items (tcibd4501m000) session.
Revision

The revision number of the New Item in the physical breakdown structure.

Note
  • This field is disabled if the header Status is set to Closed.
  • This field is applicable only if the Engineering Revisions Active check box is selected in the General Service Parameters (tsmdm0100m000) session.
  • This value is defaulted from the Lot in the Serialized Items (tcibd4501m000) session.
Copied from PBS

Indicates if this line is a copy of the original breakdown structure If yes, ERP LN selects this check box.

Note

This line is copied when the physical breakdown change is initiated.

Last Modified Date

The date/time when the data is last modified.

Note

Default value is the system date and time.

Last Modified by

The login code of the user who last modifies the line data.

Note

Default value is the system login code of the user.

 

Install

Allows you to create a new change line.

Remove

Allows you to remove the selected change line.

Replace

Allows you to replace the selected change line.

Submit

Allows you to submit the change in the selected change line.

Approve

Allows you to approve the change in the selected change line.

Reject

Allows you to rejects the change in the selected change line.

Update Physical Breakdown

Updates the actual physical breakdown structure of the selected line.

Revert Manual Change

Reverts the change with the Source of Change field set to Manual. You can revert the change only if the line Status is not set to Approved or Rejected

Generate Serial Number

Generates a new serial number for the item.