Master Routings (tsacm1101m100)

Use this session to maintain master routings.

On the appropriate menu you can start the following sessions:

  • Master Routing - Operations (tsacm2100m100) Use this session to define operations for a master routing.
  • Master Routing - Routing Options (tsacm1101m200) Use this session to create routing options for a master routing.
  • Routing Matrix (tsacm2800m000) Use this session to add operations to routing options.
Note

If you start this session by zooming, you can only find and select a record.

If the Use Master Routing Activity Duration in Depot Repair check box is selected in the Operations (tsacm2100m100) session, the duration of a master routing operation (based on the Type of Duration field in the Operations (tsacm2100m100) session) for depot repair must be considered to determine the duration of the derived work order activity. Else, the duration of the reference activity is used. In case, the duration cannot be determined from operation or reference activity, the duration is determined using:

Example

(Machine Runtime or the Labor Runtime (higher of the two) x Maintainable Quantity) + Set-up Time.

 

Master Routing

A set of operations that can be carried out. The reference activities based on which operations are added to a master routing, must have the same characteristics, such as item, functional element, and service department.

Example

All the inspections, tests, cleaning activities, assembly activities, disassembly activities, and repair activities that you can carry out on an engine.

Description

The master routing's description.

Search Argument

An alternative form of a description used for convenience during searching. A search key is usually an abbreviation, an acronym, or a mnemonic alternative to a full description.

Related topics

Activity Group

A group of reference activities with similar characteristics. For example, the Cleaning reference activity group or the Inspection reference activity group.

Activity Group

The description or name of the code.

Item

The item for which the master routing is defined.

Note

For a PCS project, you can specify the customized items if:

  • The status of the PCS project is set to Closed and the In-Service check box is selected in the General Projects (tcmcs0552m000) session, or
  • The status of the project is set to Active.
Description

The item description.

Use Fixed Price

If this check box is selected, you can set the Sales Price as the default value for the related object to which, the Master Routing is linked.

Calculated Sales Price

The sales price that is calculated based on the related resource requirements.

Note

This value is expressed in the specified Currency.

Currency

The currency in which the Sales Price and the Calculated Sales Price are expressed.

Note
  • This field is enabled and mandatory only if the Use Fixed Price check box is selected.
  • By default, the local currency is used.
Sales Price

The sales price that is set as the default value for the Master Routing. You must specify a numeric value.

Note
  • This field is enabled only if the Use Fixed Price check box is selected.
  • This value is expressed in the specified Currency.

Functional Element

A grouping of exchangeable items with identical functions. Functional elements can be used in item breakdowns, physical breakdowns, and reference activities.

Example

When a maintenance activity is defined for a configuration, a functional element can be specified. This way, the activity applies to all items covered by that functional element, and multiple, identical reference activities for similar items are avoided.

Note

Functional elements can only be defined if the Functional Elements Active check box in the General Service Parameters (tsmdm0100m000) session is selected.

Functional Element

The description or name of the code.

Service Department

The department that is responsible for the execution of a work order.

Service Department

The description or name of the code.

Buy-from BP

The description or name of the code.

Text
Created By

The name of the user who defined the master routing.

On

The date and time at which the master routing was created.

Effective Time
Expiry Time

expiry date

Note

If the expiry date is in the past, you cannot modify this master routing.

Default

If this check box is selected, you can set the default for the Master Routing.

Note
  • You can use the Set as Default Master Routing option from the Action menu to modify (select/clear) the default settings.

 

View Effective

Displays effective records only.

View All

Displays all records.

View Tree

Displays selected Master Routing in a Generic Browser Framework (GBF) tree.

Set as Default Master Routing