Delete Activities (tppss2200m000)

Use this session to delete a selected range of activities.

Select the appropriate check boxes to:

  • Delete the budget or baseline data
  • Cut the external scheduling link
  • Delete the child activities

 

Project

The code that uniquely identifies the project of which you want to delete activities.

Plan

The code that uniquely identifies the plan of which you want to delete the activities.

Activity

The From and To fields define a range of: activities.

Budget data

If this check box is selected, the budget data is deleted. The activity/budget line relationships also get deleted.

The budget data contains either

  • The budget lines of the activity in the activity budget or
  • The time-phased budget data of the activity

In both cases, the project status must be either free or active.

Note

If this check box is not selected (and the activity has either an activity budget or a time-phased budget), you cannot delete the activity.

Activity Relationships

If this check box is selected, the activity relationship data for the plan is deleted.

Baseline data

If this check box is selected, the baseline data is deleted. The baseline status of the active plan must be Free.

ESP Links

If this check box is selected, the link to the project in the external scheduling package is cut.

Child Elements

If this check box is selected, the child elements in the activity structure are also deleted.

 

Delete

Deletes the activities along with its details.

Project Selection