Sundry Cost Forecast (tpppc2596m000)

Use this session to display the cost forecast for the combination of the project and the registration date for different sundry-cost codes.

These values are used to compute forecast amounts in control enquiries and report sessions.

 

Project

The project code.

Description

The description or name of the code.

Status

The project status.

Registration Date

The date of input for the forecast deviation of costs.

Sundry Cost

The sundry costs code

Description

The description or name of the code.

Element

The element code.

Related topics

Description

The description or name of the code.

Status

The work authorization status of the element.

Activity

The activity's code.

Related topics

Description

The description or name of the code.

Status

The work authorization status of the activity.

Currency

The transaction currency

Est. Extra Cost

The amount you see here is the estimated extra costs on top of your already estimated budget.

Est. to Compl

The expected additional cost needed to complete an activity or project.

Est. at Compl

The estimated cost at completion value is used to determine the cost at the end of a project.

Approved

The confirmed forecasted cost amount.

 

Approve

Sets the transaction to approved.

Unapprove

Clears the Approved check box of the selected transaction.

Print Cost Forecast by Cost Object

Starts the Print Cost Forecast by Cost Object (tpppc2416m000) session which prints the forecast for the final result.