Element Physical Progress (tpppc1550m000)

Use this session to list the element progress for a project. This session can only be used if you entered a Progress Quantity in the Elements (tpptc1100m000) session for your element.

 

Project

The project code.

You can only select projects in which:

  • The project status is Active.
  • The Control by field in the Projects (tppdm6100m000) session is Elements Budget.
Project

The project status.

Date

The progress date. LN checks whether you can still enter progress on this project.

Element

The element code.

Phys. Progress Quantity

The budgeted number of elements.

Cumulative [Quantity]

The number of elements to be invoiced.

Cumulative [%%]

The element progress in percentages.

Completed

If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress.

If the progress does not equal 100%, you can settle the difference if:

  • The To be Settled check box in the Elements (tpptc1100m000) session is selected.
  • The selected cost object belongs to an extension for which the Extension Type field in the Extension (tpptc0110s000) session is Quantities to be Settled.
Text

If this check box is selected, a text is present.