The project code.
You can only select projects in which:
- The project status is Active.
- The Control by field in the Projects (tppdm6100m000) session is Elements Budget.
Element Physical Progress (tpppc1550m000)Use this session to list the element progress for a project. This session can only be used if you entered a Progress Quantity in the Elements (tpptc1100m000) session for your element.
Project The project code. You can only select projects in which:
Project The project status. Date The progress date. LN checks whether you can still enter progress on this project. Element The element code. Phys. Progress Quantity The budgeted number of elements. Cumulative [Quantity] The number of elements to be invoiced. Cumulative [%%] The element progress in percentages. Completed If this check box is selected, the production of the selected element is assumed to be completed. If it is not completed, you can still enter a progress. If the progress does not equal 100%, you can settle the difference if:
Text If this check box is selected, a text is present.
| |||