This is a traffic light based metric which gives the user a
graphical view of the overall health of the project.
Traffic Light indicators:
Green: Project is on schedule
Yellow: Project requires attention
Red: Project requires urgent attention
Project Manager Dashboard indices:
Effort
SPI
CPI
VAC
OTP
Calculation
(Earned
Value hours - Actual Hours)/Earned Value * 100
Earned Value/Planned
Value
Earned Value / Actual Cost
(Budget at Completion –
Estimate at completion)/ Budget at Completion * 100
No. of activities
completed till date / No. of activities planned to be completed as on
date.
Green
> = 0
>= 1
>=
1
>0
> =1
Yellow
= -5 to
0
=0.95 to 0.99
=0.95 to 0.99
= -5 to 0
= 0.95
to 0.99
Red
< -5
< 0.95
<
0.95
< -5
< 0.95
The indicators list additional information for each
metric:
You can drill-down to Effort by Project from Effort.
You can drill-down to Earned Value by Project from
SPI.
You can drill-down to Earned Value by Project from
CPI.
You can drill-down to Estimate at Completion by Project from
VAC.
You can drill-down to Activity Performance from OTP.
Effort by Project
Effort by Project
The Effort by Project trend graph displays the planned, earned
and actual labor hours by project for a period of time (start date of project
to the current date). On a specific date, if the planned hours exceed the
earned hours, the graph indicates that the hours are not consumed as planned.
On a specific date, if the actual hours exceed the earned hours, the graph
indicates an hours overrun.
Earned Value by Project
Earned Value by Project
To view the Earned Value by Project metric, click Schedule
Performance Index or Cost Performance Index. This metric displays the budget
that must be spent, based on the amount of work completed on a specific date.
This metric also indicates the budget consumption in the future. The Earned
Value metric provides the project manager with an effective method to measure
performance and predict results. This helps in creating comprehensive progress
reports and early identification of overruns. Cost and time allocation
decisions can also be made in advance. The Earned Value metric is a useful tool
to predict the outcome of projects with regards to time to completion, cost to
completion and expected final costs.
Estimate at completion by Project
Estimate at completion by Project
This bar chart displays the BAC, EAC, and VAC values for the
project selected in the Overall Project Performance metric. Variance at
Completion (VAC) value = Budget at Completion (BAC) - Estimate at Completion
(EAC). A negative variance at completion indicates a cost overrun. A positive
variance at completion indicates a cost under-run.
Activity Performance
Activity Performance
When the user clicks On Time Performance, by default, the
Activity Performance metric is displayed. The Baseline Execution Index is
similar to the Schedule Performance Index (SPI) calculation, but instead of
amounts, this index is calculated based on the number of tasks. This metric
measures only the number of tasks planned and completed during a specific time
period. Activity Performance is calculated based on the cumulative no. of
milestones / activities actually completed as compared to the no. of
milestones/activities planned to be completed on a periodical basis. The user
can also view the Milestone Performance metric using the toggle
option.
Milestone Performance
Milestone Performance
When the user clicks On Time Performance, by default, the
Activity Performance is displayed. However, the user can view another metric
Milestone Performance using the toggle option. These metrics indicate the
progress of the activities or milestone according to the defined baseline plan.
The results are displayed on a periodical basis, and are based on the
cumulative number of milestones/activities actually completed as compared to
the number of milestones/activities planned to be completed.