Overall Project Performance

This is a traffic light based metric which gives the user a graphical view of the overall health of the project.

[...]

Traffic Light indicators:

  • Green: Project is on schedule
  • Yellow: Project requires attention
  • Red: Project requires urgent attention

Project Manager Dashboard indices:

EffortSPICPIVACOTP
Calculation(Earned Value hours - Actual Hours)/Earned Value * 100Earned Value/Planned ValueEarned Value / Actual Cost(Budget at Completion – Estimate at completion)/ Budget at Completion * 100No. of activities completed till date / No. of activities planned to be completed as on date.
Green> = 0>= 1>= 1>0> =1
Yellow= -5 to 0=0.95 to 0.99=0.95 to 0.99= -5 to 0= 0.95 to 0.99
Red< -5< 0.95< 0.95< -5< 0.95

 

The indicators list additional information for each metric:

  • You can drill-down to Effort by Project from Effort.
  • You can drill-down to Earned Value by Project from SPI.
  • You can drill-down to Earned Value by Project from CPI.
  • You can drill-down to Estimate at Completion by Project from VAC.
  • You can drill-down to Activity Performance from OTP.
Effort by Project
 

Effort by Project

The Effort by Project trend graph displays the planned, earned and actual labor hours by project for a period of time (start date of project to the current date). On a specific date, if the planned hours exceed the earned hours, the graph indicates that the hours are not consumed as planned. On a specific date, if the actual hours exceed the earned hours, the graph indicates an hours overrun.

[...]

 

 
   
Earned Value by Project
 

Earned Value by Project

To view the Earned Value by Project metric, click Schedule Performance Index or Cost Performance Index. This metric displays the budget that must be spent, based on the amount of work completed on a specific date. This metric also indicates the budget consumption in the future. The Earned Value metric provides the project manager with an effective method to measure performance and predict results. This helps in creating comprehensive progress reports and early identification of overruns. Cost and time allocation decisions can also be made in advance. The Earned Value metric is a useful tool to predict the outcome of projects with regards to time to completion, cost to completion and expected final costs.

[...]

 

 
   
Estimate at completion by Project
 

Estimate at completion by Project

This bar chart displays the BAC, EAC, and VAC values for the project selected in the Overall Project Performance metric. Variance at Completion (VAC) value = Budget at Completion (BAC) - Estimate at Completion (EAC). A negative variance at completion indicates a cost overrun. A positive variance at completion indicates a cost under-run.

[...]

 

 
   
Activity Performance
 

Activity Performance

When the user clicks On Time Performance, by default, the Activity Performance metric is displayed. The Baseline Execution Index is similar to the Schedule Performance Index (SPI) calculation, but instead of amounts, this index is calculated based on the number of tasks. This metric measures only the number of tasks planned and completed during a specific time period. Activity Performance is calculated based on the cumulative no. of milestones / activities actually completed as compared to the no. of milestones/activities planned to be completed on a periodical basis. The user can also view the Milestone Performance metric using the toggle option.

[...]

 

 
   
Milestone Performance
 

Milestone Performance

When the user clicks On Time Performance, by default, the Activity Performance is displayed. However, the user can view another metric Milestone Performance using the toggle option. These metrics indicate the progress of the activities or milestone according to the defined baseline plan. The results are displayed on a periodical basis, and are based on the cumulative number of milestones/activities actually completed as compared to the number of milestones/activities planned to be completed.

[...]

 

 
   
CPI/ SPI Trend by Project
 

CPI/ SPI Trend by Project

The cost performance index (CPI) and schedule performance index (SPI) values are calculated using the Planned Value, Earned Value, and Actual Value of the selected project; for the specified period.

Cost Performance Index shows the value earned for the amount spent on the project.

Schedule Performance Index shows whether the project can be delivered late, on time, or early.

To view the CPI/ SPI Trend by Project metric, go to Overall Project Performance > CPI (or) SPI > Earned Value by Project > CPI\ SPI Trend.

CPI = Earned Value (EV)/ Actual Costs (AC)

  • If CPI < 1, the costs are not incurred efficiently on the project
  • If CPI = 1, the project is on track
  • If CPI > 1, the costs are incurred efficiently on the project

SPI = Earned Value (EV)/ Planned Value (PV)

  • If SPI < 1, the project is behind schedule
  • If SPI = 1, the project can be completed on the date scheduled by the plan
  • If SPI > 1, the project can be completed prior to the scheduled date
[...]