Work Center Input/Output Control (tisfc3510m000)

Use this session to see a summary of the planned and actual input and output values for a work center.

Note

If you want to see input/output data for a machine, use the Machine Input/Output Control (tisfc3520m000) session.

 

Work Center

The work center for which you want to compare actual and planned inputs and outputs. Note that you can only see data for work centers whose Critical in Master Planning check box is selected in the Work Centers (tirou0101m000) session.

Description

The work center for which you want to compare actual and planned inputs and outputs. Note that you can only see data for work centers whose Critical in Master Planning check box is selected in the Work Centers (tirou0101m000) session.

Lead Time

The desired queue that is defined for the work center in the Work Centers (tirou0101m000) details session.

Planned Input

The total input quantity of a work center/machine for operations that is planned to be Ready to Start during the target period.

Actual Input

The total input quantity of a work center/machine for operations that are Ready to Start during the target period.

Input Cum. Dev.

The sum of the differences between the planned input and the actual input for the current target period and all the target periods before the current one for which you have data.

Planned Output

The total output quantity that you plan to report complete, for operations at a work center/machine during the target period.

Actual Output

The total output quantity that is reported complete, for operations at a work center/machine during the target period.

The value of the actual output depends, among other things, on the setting of the Include Partial Completions check box in the Generate Work Center Input/Output Control (tisfc3210m000) session.

Output Cum. Dev.

The sum of the differences between the planned output and the actual output for the current target period and all the target periods before the current one, for which you have data.

Planned Queue

The planned input minus the planned output of a work center/machine.

Actual Queue

The actual input minus the actual output of a work center/machine. Note that the queue includes active operations as well as operations waiting to be carried out.

Queue Deviation

The difference between the planned queue and the actual queue on the generation date, that is actual queue minus planned queue.

Desired Queue Dev
Available Capacity

The total capacity available, for either a day or a week, usually based on the work center calendar.

Demo. Load Factor

Combined efficiency and utilization. The ratio of actual output to available capacity, for an operation performed at a given work center or machine.

Ending Date

The last day of the target period.

Number of Operators

The number of operators that is available on the work center.

Man Hours

The number of man hours that are desired on the work center, given the desired queue.

Man hours = Number of operators on the work center * Desired queue

Number of Machines

The number of machines that is available on the work center.

Machine Hours

The number of machine hours that are desired on the work center, given the desired queue.

Machine hours = Number of machines on the work center * Desired queue

Planned Input

The total input quantity of a work center/machine for operations that is planned to be Ready to Start during the target period.

Actual Input

The total input quantity of a work center/machine for operations that are Ready to Start during the target period.

Input Cum. Dev.

The sum of the differences between the planned input and the actual input for the current target period and all the target periods before the current one for which you have data.

Planned Output

The total output quantity that you plan to report complete, for operations at a work center/machine during the target period.

Actual Output

The total output quantity that is reported complete, for operations at a work center/machine during the target period.

Output Cum. Dev.

The sum of the differences between the planned output and the actual output for the current target period and all the target periods before the current one, for which you have data.

Planned Queue

The planned input minus the planned output of a work center/machine.

Actual Queue

The actual input minus the actual output of a work center/machine. Note that the queue includes active operations as well as operations waiting to be carried out.

Queue Deviation

The difference between the planned queue and the actual queue on the generation date, that is actual queue minus planned queue.

Desired Queue Dev
Available Capacity

The total capacity available, for either a day or a week, usually based on the work center calendar.

Demo. Load Factor

Combined efficiency and utilization. The ratio of actual output to available capacity, for an operation performed at a given work center or machine.