Order Distribution (tisfc0105m100)

Use this session to view the production order distribution.

Note

If the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session, and if you manually change the peg distribution, a window is displayed in which you must specify a reason code.

 

Production Order

The production order that uses the materials.

Order Status

The order status of the production order.

Allowed values

Order Status

Item

The item produced by the production order.

Quantity Ordered

The quantity ordered for the distribution line.

The total quantity ordered on the distribution lines makes up the quantity on the header. When the quantity ordered on the distribution lines is changed the total on the header is updated.

Note

You can reduce the order quantity for released orders, for example, from 10 to 7 pieces. However, you cannot change the order quantity to a value less than the quantity that is reported as complete on an operation. If you want to enter a ordered quantity that is less than the quantity on an operation, you must reduce the quantity on the operation first. To do this, you must take the following into account:

  • If the operation status is Completed, you must reset the operation status to Active.
  • If a count point is used on the operation, you must first remove the count point before you can complete the order with a lower quantity.
Backflushed

The quantity already issued by backflushing for the effectivity unit.

Warehouse

The warehouse in which the item is stored after completion.

WMS Controlled

If this check box is selected, you defined in the Warehouses (tcmcs0503m000) session that an integration with a Warehouse Management System (WMS) exists.

Standard Configuration

If this check box is selected, all effectivity units that are listed in this session concern an item that has a standard configuration.

Distribution Line

The number of the distribution line.

Project
Element
Activity
Project Peg Origin

The origin of the project peg for the production order.

Allowed values

Project Peg Origin

Quantity Ordered
Quantity Reported on Last Operation

The number of items for the specific effectivity unit that is reported as complete on the last operation but that have not been delivered to the warehouse yet.

Quantity Delivered

The quantity already delivered for the distribution line.

Quantity to Deliver

The quantity to be delivered to the warehouse for the distribution line.

You can modify the value of this field in the Order Distribution (tisfc0105m000) details session, if the Order Status is greater than or equal to Released.

Quantity Rejected

The quantity that is scrapped. These end items cannot be sent to quarantine for possible reworking.

Related topics

Effectivity Unit

effectivity unit

Zero (0) indicates the standard configuration.

Item

The item produced by the production order.

Unit Series
Unit Sequence

The sequence number of the effectivity unit.

Lot Code

The lot to which the completed products belong.

You can modify the value of this field in the Order Distribution (tisfc0105m000) details session, if the Order Status is greater than or equal to Released.

Note

The Lot Code can not be manually modified if Project Pegging is selected on company level.

Quantity Initial

The order quantity for the effectivity unit at the time the production order was released.

Quantity On Order

The number of items for the specific effectivity unit on the production order.

Quantity to Backflush

The quantity to be issued by backflushing for the effectivity unit.

Quantity Backflushed

The quantity already issued by backflushing for the effectivity unit.

 

Requirements
Where-Used in Effectivity Statement
Print Identical Production Configurations
Change Ordered Quantity

Generate Lot Code

Pegging - Upstream

Click Pegging - Upstream to start the GBF browser in which you can view the production order's supply orders, that is, the preceding production orders and/or purchase orders.

Click Pegging - Downstream to view the production order's demand orders, that is, the successive production orders and/or sales orders.

You can only start pegging if the following is true:

For more information, refer to Pegging for planned orders.

Pegging - Downstream

Click Pegging - Downstream to start the GBF browser in which you can view the production order's supply orders, that is, the preceding production orders and/or purchase orders.

Click Pegging - Downstream to view the production order's demand orders, that is, the successive production orders and/or sales orders.

You can only start pegging if the following is true:

For more information, refer to Pegging for planned orders.