Report Production Schedules Completed (tirpt1201m000)

Use this session to report all production orders as Completed in a production schedule. You can also report a specific operation as Completed in a production schedule.

 

Item

The repetitive item for which the production schedule is valid.

Item Period

The period's year for which reporting must be performed.

The period shown elsewhere in this session can be different from the period displayed here, because you can link different production schedules to scheduling areas than to items.

Item Period

The code that represents a range of time in the period.

Scheduled SFC

The sum of ordered quantities of all SFC orders that concern the item in the Item field or the item/scheduling area combination for the selected period.

Start Date

The start date of the period in which the order delivery dates fall.

Quantity to Deliver

The sum of item quantities that are reported as complete. The quantities are not yet received in the warehouse, unlike the quantity in Quantity Delivered field. The item quantities concern all SFC orders with order status Active for the item in the Item field.

End Date

The end date of the period in which the order delivery dates fall.

Quantity Rejected

The sum of the quantity rejected of all SFC orders whose status is Active. The orders concern the item in the Item field.

These rejects consist of the following parts:

  • The quantities entered in the Quantity Rejected field of the Report Operations Completed (tisfc0130m000) session for all the operations of the production order.
  • The quantities rejected in the Product Testing and Control module.
Sched. Area

The code of the scheduling area.

In the Item - Routings (tirou1101m000) session you can link the scheduling area to a routing. The orders for the items linked by the routing to the scheduling area are shown in the Production Schedules (tirpt1500m000) session if the routing is defined for an order in one of the following:

  • The Shop Floor Control module
  • The Master Planning module
  • The Order Planning module
  • Warehousing

The orders for which a routing is defined that are linked to a scheduling area are shown in the Production Schedules (tirpt1500m000) session.

Related topics

Sched. Area

The description or name of the code.

Quantity Remaining

The quantity that still must be reported Completed concerning the item in the Item field. That quantity equals the sum of the total scheduled quantity and the quantity that is delivered, minus the quantity rejected.

Scheduled at Day End

The sum of the quantity ordered of all orders concerning the item in the Item field that have a delivery date before or on the current date.

For Operation/Task

The position number of the operation you report completed. If you do not select an operation, the last operation's data is taken by default.

/

The task you want to report as Completed. If you select an operation, you must select its tasks as well. An operation can have several tasks, because one item can have several orders and several routings.

Scheduled at Day Start

The sum of the quantity ordered of all orders concerning the item in the Item field that have a delivery date before the current date.

Scheduled Today

The quantity ordered concerning the item in the Item field that is scheduled on the current date. This quantity equals the quantity in the Scheduled at Day End field minus the quantity in the Scheduled at Day Start field.

Quantity Completed

The quantity of items reported with the status Completed. Items that are reported as completed can proceed to the upcoming operation.

Direct Process Inbound

If this check box is selected, the quantity that is completed is posted to inventory. The inbound procedure is processed automatically.

Complete Production Order

If this check box is selected, all orders of the production schedule must be reported as complete. After the operations of all orders from the production schedule are reported as complete, the check box is selected by default.

Print Label during Report Orders Completed

If this check box is selected, a label is printed for each production order in the schedule that is completed.

Complete Operation

Indicate in this field if the operation must be reported as complete.

Once you report an operation as complete, the capacity load is lifted. The material requirements for the subsequent operations are adjusted because of the rejects from the preceding operations.

Lot Code

A number of items produced and stored together that are identified by a (lot) code. Lots identify goods.

Quantity Delivered

The sum of item quantities that are reported as complete and that are delivered to the warehouse. The item quantities concern all SFC orders with order status Active for the item in the Item field.

 

Interactive Reporting

Click to interactively report production schedules as Completed. LN provides an option (yes/no) to report the completion of operations. Interactive reporting is done with the Report Production Orders Completed from Production Schedule (tirpt1502m000) session.

Automatic Reporting

Click to automatically report production schedules as Completed. The previous operations are automatically reported as Completed, based on the quantity completed in this session.

Generate Lot

Click to generate a lot number.