Validate Subcontracting Settings of Routing Operations (tirou1215m000)

Use this session to validate routings with subcontracting operations. Any errors are printed in a report.

Checks

The session checks the settings for all operations performed on work centers for which Work Center Type is Subcontracting Work Center.

Which checks are performed depends on the Subcontracting with Material Flow check box in the Items - Production (tiipd0101m000) session.

Subcontracting without material flow support

In case of subcontracting without material flow support, LN checks whether the following conditions are met:

  • For each subcontracted operation, an item of type Subcontracted Service must be present in the Subcontracting Rates (ticpr1160m000) session.
  • Subcontracting rates must exist for the subcontracting work center.
Subcontracting with material flow support

In case of subcontracting with material flow support, LN performs these checks:

  • LN checks BOM loops: a sub item is not allowed to occur in the parent path.

    If the main item has subcontracting with material flow support, LN checks all BOM levels until it finds a phantom, for which Subcontracting with Material Flow is "No". LN then checks the routing of this phantom and searches, one level higher in the BOM, for the next phantom.

  • The following checks are performed:

    Note: For non-Standard Configuration routings, these checks are performed only if you select Specific in the Configuration field, and if the operation is valid for the selected Effectivity Unit.

    • Subcontracting rates must exist for the subcontracting work center.
    • The Subassembly field in the Routing Operations (tirou1102m000) session must have a value if the operation is a subcontracting operation, or the next operation is a subcontracting operation. Note: this rule does not apply if no next operation exists or the next operation is a subcontracting operation for the same subcontractor.
    • If the last operation of a main item or phantom routing is subcontracted, the Subassembly Warehouse field in the Routing Operations (tirou1102m000) session must have a value.
    • Each item entered as subassembly in the Subassembly field in the Routing Operations (tirou1102m000) session must have a cost price and cost price structure.
    • If a phantom has a standard routing, the project segment of subassemblies defined on the phantom's routing must be empty or equal to the project segment of the end item.
    • If an operation is performed on a subcontracting work center, that work center must have a shop floor warehouse.
    • For the shop floor warehouse of a subcontracting work center to which a subassembly is moved, the subassembly's supply system must be Order Controlled/Single.
    • If a subassembly's supply warehouse or a subcontracting work center's shop floor warehouse have been defined, they must be equal to the warehouse defined for the subassembly in the Items - Ordering (tcibd2500m000) session.

 

From Manufactured Item

The range of items for which the routing operations are validated.

Routing

The range of routings to validate.

Configuration

This field determines whether the standard configuration is validated or a specific effectivity unit.

Effectivity Unit
Effective Date

The session validates the settings which are effective on the date you specify here.

Print Errors Only

If this check box is selected, the session reports only the errors, if any. Warnings are not printed. If this check box is cleared, warnings are also printed.

 

Validate

Starts validating.