| Project Surcharges (tipcs3120m000)Note If you have started
the session by zooming, you can only find and select a record. If the project
is of the Budget type, it is not possible
to enter actual surcharges. If no project is filled, general surcharges for all
projects, without their own surcharges are defined. In the detail session
you can maintain cost price surcharges by project, and by surcharge type, for
performing a project calculation. These surcharges - which can be recorded for
the estimated and actual project calculation - are applied to the total
estimated or actual costs for a project. They form the basis for extra costs or
discounts (in percentage of amounts) in the project's cost price structure. Project A collection of manufacturing and purchasing actions that are
performed especially for a particular customer order. A project is initiated by
a customer order for items having a To Order order policy. The purpose of a project is to plan and coordinate the production
of these items. For a standard-to-order production, the project is only
used to link the item with the customer order. Otherwise, a project can
include: - Customized item data (BOMs and routings)
- Project planning (activity planning)
A budget is a special type of project. A budget is used to
plan and estimate, not to carry out production. Surcharge Type The type of cost price surcharge indicates whether there is an
estimated or actual surcharge on the cost price for the project. Sequence Each time you enter a new project surcharge, the detail session
will be activated. The sequence field in this detail session will automatically
be filled with 10 or a multiple thereof. You can always overwrite this value.
Once you have completed executing the detail session, the sequence number will
be filled in the overview session. Variable Cost Specifies whether the project surcharges are variable or fixed. If this check box is selected, the surcharge is
considered a variable cost. Otherwise, it is considered a fixed cost. Note Fixed costs are only
included in the cost price of a project if the Include Fixed Costs in Project Valuation parameter is selected. Calculation Line Type Indicates how the calculation line in the computation of the
project surcharge is taken into account. Currency The currency in which the amount is expressed. Currency The description of the currency. Surcharge Bases Present If this check box is selected, a surcharge base is present. A
set of cost components that applies
to the project surcharge is then defined. Note A surcharge base can
only be present if the value of the Surcharge Method field is set to % of Selective Costs. Surcharge Amount The project surcharge expressed as an amount. If you chose: - Surcharge in the Calculation Line Type field
- Fixed Amount in the Surcharge Method field
You can enter a cost
price surcharge in the surcharge amount field. Surcharge Percentage The project surcharge expressed as a percentage. Surcharge Method The method of computing the project surcharge. Surcharge Component The cost component to which the project surcharge is linked.
Select the desired cost component, under which the computed cost price
surcharge must be stored when calculating. Only cost components with the cost
type Surcharge on Material Costs, Surcharge on Operation Costs, or General Costs are allowed. Project Status The current stage of the project. | |