| Offsetting OptionsInitial If this option is selected, the Initial Start Date must be specified. Note - The Initial Start Date must be in the future.
- By default, the Initial Start Date is the planned start time of the
first position on the last segment of the assembly line. If this date is in the
past, it is changed to the current date and time + 5 minutes, or the first
available work time in the calendar.
- This option can only be selected if no assembly has started
on the first segment of the assembly line.
Continuous If this option is selected, the new line sequence for each new
segment is synchronized with the planned end date of the last completed
position on that segment. Note Continuous is the only option available if assembly has
started, but no orders are completed. Backlog If this option is selected, new orders are sequenced from the
date you specify in the Replan Start Date field. Note The Replan Start Date must be in the future. By default, it
is the current date and time + 5 minutes, or the first available work time in
the calendar. This option is only available if the previous segment was
completed. Actual Times If this option is selected, a new line sequence is synchronized
for each new segment with the last completion date on that segment. Note This option is only available if orders have already been
completed on the last segment of the assembly line.
| |