| | Print Estimated vs. Actual Material Costs (ticst0401m000)Use this session to print a report that
compares the estimated material costs and the actual material costs for a
production order. Select the range of production orders for which you want to
print the costing data. Then indicate: - If you also want to
print the material costs by (costing) work center.
- If only closed orders
must be printed.
- If LN must recalculate the
estimates on basis of the progress of the order.
Costing Work Center A work center, when linked to a planning work center, that is
used to calculate the end item unit costs, WIP transfers, and production
results. The financial transactions related to production orders are then
posted to the costing work center. The link between a costing work center and a planning work
center enables you to replan production order operations. If required, you can
change the work center that is used to carry out an operation without
disturbing the costing process. Print Currency Select in which currency the costs must be printed. Note - If the Currency System of
your company is Single or Dependent, this field is
enabled.
- If the Currency System of
your company is Independent, this
field is disabled and displays Reference.
Currency LN prints
the cost amounts in this currency. Note - In the Print Currency field you can select in which currency the costs must be
printed.
- If you select Any in the Print Currency field, you can enter a currency in this field.
Print only if actual costs are higher then % of estimated costs Production orders are printed on the report if the production
order's total actual material costs are higher then the specified estimated
costs' percentage. Print only if actual costs are lower then % of estimated costs Production orders are printed on the report if: - The production order's total actual material costs are
lower then the specified estimated costs' percentage.
- The production order's status is at least To be Completed.
Low costs can indicate costs that were incorrectly
registered, for example, if backflushing is forgotten. Note If this check box is selected, production orders that
are Active, Released,
or Planned are never printed. Print corrected Estimates (based on progress) If this check box is selected, LN corrects the calculated estimates on basis
of the quantities reported in the order planning. Print Closed Orders Only If this check box is selected, LN only prints production orders with the Closed status. Actual Closing date Production orders are printed on the report if they are closed
within the specified date range. Include Supplied by Subcontractor If this check box is selected, then estimated materials
that are supplied by the subcontractor will be printed. Include Customer Owned If this check box is selected, the customer owned
estimated materials will be printed. Include Print Only If this check box is selected, estimated materials with Material Control Method Print Only will be printed. | |