Purchase Order Line Quantities and Dates (tdpur4101m300)Use this session to have an overview of the (confirmed) quantities and dates for a purchase order line. With this session, the following can be carried out:
Note This session can only be started if the Use Confirmation (Purchase) check box is selected in the Implemented Software Components (tccom0100s000) session.
Buy-from Business Partner Purchase Order The number of the purchase order. Position The number used to identify the position of the order line on the sales or purchase order. Sequence The number used to identify in detail the position number of a sales order (delivery) line or a purchase order line (detail). Item Warehouse Required Quantity The ordered quantity that is required by the buy-from business partner. Required Quantity Unit The unit in which the Required Quantity is expressed. Confirmed Quantity The ordered quantity that is confirmed by the buy-from business partner. Confirmed Quantity Unit The unit in which the Confirmed Quantity is expressed. Confirmation Accepted If this check box is selected, the Confirmed Quantity is accepted by the buyer. No further negotiations are possible with the buy-from business partner. Minimum Required Quantity The ordered quantity that is at least required by the planner. This field is used for information purposes only. Minimum Required Quantity Unit The unit in which the Minimum Required Quantity is expressed. Order Date The date on which the order is manually specified or is automatically generated. Note
Default value
Planned Receipt Date The planned date on which the items on the order/schedule line are planned to be received. The planned receipt date cannot occur before the order date/schedule generation date. Confirmed Receipt Date The receipt date for the items, which is confirmed by the buy-from business partner or confirmed to the sold-to business partner. This date is used for several purposes:
Changed Receipt Date The new receipt date that is used if the supplier cannot comply with the agreed receipt date and states a new receipt date. Together with the planned and/or confirmed receipt date, the changed receipt date is the basis for determining the vendor rating, and the planned inventory movements. In addition, this date is also used in the reminder procedure. Minimum Required Receipt Date The receipt date that is at least required by the planner. This field is used for information purposes only. Order Confirmation Date The date on which the buy-from business partner confirmed the purchase order, or the date on which the sales order is confirmed to the sold-to business partner. The order confirmation date is used for the calculation of order confirmation objective ratings in vendor rating. The buy-from business partner is given a rating according to the time interval between the order date and the order confirmation date. Approved If this check box is selected, the purchase order line is approved by an authorized approver. Canceled If this check box is selected, this purchase order line is canceled. Cancellation in Process If this check box is selected, this purchase order line cannot be canceled because it includes one or more supplier stage payment lines with the Released or Invoiced status. When these lines receive the Processed status, the purchase order line is canceled. For purchase order lines with this check box selected, you can specify correction stage payment lines in the Supplier Stage Payments (tdpur5120m000) session to credit the invoiced amounts. Invoice by Stage Payments If this check box is selected, the purchase order line item must be invoiced by stage payments. Peg Distribution If this check box is selected, a peg distribution is linked to this purchase order line. Note Manual changes in this session can affect the linked peg distribution. If this is the case, and if the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session, a window is displayed in which you must specify the change reason. The project peg changes and the reason codes are logged in the Cost Peg Audit History (tpctm2500m000) session.
| |||