Manufacturing Control

This topic lists the differences topics for Manufacturing between Infor LN 10.2.0 and Infor LN 10.2.1.

Changed functionality in Production Order Distribution

Production Warehouse Order Distribution

Infor LN 10.2.1

The Production Warehouse Order Distribution (timfc0105m000) was added to facilitate the storing of project pegs for material issues and end item receipts for production orders with distribution lines containing project pegs.

For Infor LN 10.2.1 a distribution has been added below Production Warehouse Orders (timfc0101m000) session to reduce the number of outbound/inbound lines. The distribution does not contain an effectivity unit, but only the project peg attributes.

Because the number of effectivity units per production order is restricted to one with project pegging implemented.

  • The number of product warehouse orders is independent of the number of distribution lines.
  • A combination of lines with and without effectivity units is no longer possible; all lines for one order will now have the same effectivity unit.

When a production order distribution containing project pegs is created only one production warehouse order is generated for each distribution line. This applies to both production order distributions lines as to material distribution lines.

  • If an order is project pegged, a material does not inherit the project pegs but material distribution lines are created because of the presence of an effectivity unit. In this case no production warehouse order distribution is created.
  • If an order has a distribution line without project peg, a production warehouse order distribution is created when there are other lines with project pegs.

When the end item receipts or material issues are done, more production warehouse orders may be created because of partial receipts or issues. The production warehouse order distribution of these production warehouse orders will only contain lines for distribution lines on which materials are received or issued.

For the creation of inbound and outbound lines for production orders and the creation of warehouse orders in Warehousing production warehouse orders are needed. For different order/material distribution lines, only one sequence number is created in for project pegged production orders.