Billing rate in overhead calculation

Infor LN 10.3

The Applied rate (internal) and the Billing rate (external) options are not available to calculate the overhead costs.

Infor LN 10.4

You can use the Applied rate (internal) and the Billing rate (external) to calculate the overhead costs.

  • The applied rate is used to calculate the internal overhead costs for the contract/ project. These overhead costs are added to the cost on the contract/ project.
  • The billing rate is used to calculate the external billable overhead costs. These overhead costs can be invoiced to the business partner.