Status of purchase document by peg

In Infor LN 10.4, the Status field is added to the Procurement Data by Project Peg (tdpur5500m000) session.

For a purchase document that is linked to a peg, this new field shows the status or the next activity to be executed for the purchase document.

Example
ProjectP00004
ElementE00567
ActivityA45634

 

DocumentStatus
Purchase order linePO3399710/1Approve Purchase Orders
Requisition lineREQ3045620Created
RFQ lineRFQ3155220/0In Process

 

For more information on the status or next activity, refer to the purchase document's session. You can start a document's session by clicking Open Document on the appropriate menu of the Procurement Data by Project Peg (tdpur5500m000) session.