Landed costs on RFQs

In Infor LN 10.4, you can use landed costs with requests for quotation (RFQs).

The new Apply Landed Costs on Request for Quotation check box in the Landed Costs Parameters (tclct0100m000) session determines if landed costs can be linked to an RFQ.

Landed costs can be charged by the supplier of the goods (bidder), and also by a third party supplier, such as the carrier responsible for the transport of the goods. Bidder landed costs can be negotiated in the RFQ negotiation process. Third party landed costs cannot be negotiated.

LN considers the bidder and third party landed costs when comparing and ranking the received RFQ responses.

Note
  • An RFQ includes these objects: RFQ header, RFQ line, RFQ bidder, RFQ response, and RFQ negotiation. Landed costs can be linked only to an RFQ bidder, RFQ response, and RFQ negotiation.
  • You can view the bidder landed costs and the third party landed costs separately for the linked landed costs in the RFQ Responses (tdpur1506m000), RFQ Negotiations (tdpur1606m000), and RFQ Negotiations (tdpur1109m000) sessions.

For more information, refer to Landed costs – requests for quotation (RFQs).