This code indicates that LN displays the item order plan for the actual scenario.
Item Order Plan (cprrp0520m000)Use this session to get a time-phased overview of your order planning, which lists overview values for demand and forecast on the one hand, and scheduled receipts (actual orders) and planned supply (planned orders) on the other. Select the Simulate field to change the above values and see what the results are for the projected inventory. The order quantities of the orders that fall in one period are added up. You can select one of several sets of predefined period lengths. Instead of selecting a time period, you can also choose to display a detailed overview in which each order is listed separately. If you click the Change Company command, you zoom to the Change Company (cpcom1200s000) session. Here you can switch to a different logistical company. Note
If you move the production plan or the purchase plan to planned orders with the Convert Master Plan to Planned Orders (cprmp2240m000) session, the resulting orders have the order type Production Plan and Purchase Plan in the current session. Customized items derived from this item To view all transactions for an item and the customized items derived from the item, click the Include Derived Items button.
Scenario This code indicates that LN displays the item order plan for the actual scenario. Plan Item An item with the order system Planned. The production, distribution, or purchase of these items is planned in Enterprise Planning based on the forecast or the actual demand. You can plan these items by means of the following:
Plan items can be one of the following:
A group of similar plan items or families is called a product family. The items are aggregated to give a more general plan than the one devised for individual items. A code displayed by the item code's cluster segment shows that the plan item is a clustered item that is used for distribution planning. Project Peg Project Allowed values Element Allowed values Activity Allowed values Horizons Time Fence The date to which the time fence extends. You can specify the time fence in the Items - Planning session. Forecast Time Fence The date to which the forecast time fence extends. You can specify the forecast time fence in the Items - Planning session. Note The forecast time fence is only used if the item has an item master plan. Order Horizon The date to which the order horizon extends. You can specify the order horizon in the Items - Planning session. Planning Horizon The date to which the planning horizon extends. You can specify the planning horizon in the Items - Planning session. Whenever you move a plan to planned orders, you must be able to see the orders before you transfer them to execution level. This is why the item order plan uses the planning horizon. If the item does not have an item master plan, the planning horizon is equal to the order horizon. ATP Horizon Net Change Date The net change date for order planning (see the Items - Planning session). General Planner The employee or department responsible for planning the production, purchase and distribution of items. The planner takes into account the inventory levels, availability of materials, and capacities of resources, and reacts on signals such as rescheduling messages that LN generates. Cost Price The cost incurred by manufacturing or purchasing a single item (inventory valuation). Note LN retrieves the value of the current field from the Cost Price field in the Items - Costing (ticpr0107m000) session. Actual Supply Source The actual supply source of the item. If you define a date effectivity line in the Date-Effective Item Data (tcibd0510m000) session, the actual source can be time-dependent. Inventory on Hand The physical quantity of goods in one or more warehouses (including the inventory on hold).
Overview Date The end date and time of the period. The displayed periods are defined by the period length (specified in the Scenario field) and the start date of the scenario. The first displayed period starts on the start date of the scenario. The last displayed period is determined by the planning horizon. The period in which the planning horizon falls is the last displayed period. Note If you chose the Detail option in the Scenario field, the last displayed line is the last order that occurs in the order horizon. Simulate You can use this field to enter additional demand or an additional supply of the plan item. You can simulate an additional demand by entering a negative quantity. You can simulate an additional scheduled receipt or an additional planned supply by entering a positive quantity. If you want to see the results of the simulation, click the Update button. Order Type The order type of the order involved. Allowed values Order Number This field is filled when you choose a detailed overview, or the period of the planned inventory movements contains only one order. This field contains the order number. Order Status The status assigned to a planned order in Enterprise Planning. The order status can either be:
Allowed values Demand The demand for the plan item expressed in the number of items. Note If the Scenario field has the value Detail, you can see where the demand originates in the Order Number field and the Order Type field on the Detail tab. Supply The sum of the scheduled receipts and the planned receipt. Planned Available The expected inventory level at the end of a plan period. Note that the projected inventory of plan periods that are entirely in the past equals the inventory on hand. ATP Available-to-promise calculated based on the content Planned Available field. Note The values of the ATP in Item Order Plan (cprrp0520m000) are not always equal to the quantities that are calculated during the ATP check executed during the sales order entry or reported by the ATP Handling (cprrp4800m000) session. The difference can be due to these reasons:
Safety Stock The buffer inventory necessary to meet fluctuations in demand and delivery lead time. In general, safety stock is a quantity of inventory planned to be in inventory to protect against fluctuations in demand or supply. In the context of master production scheduling, safety stock is the additional inventory and capacity planned as protection against forecast errors and short-term changes in the backlog. Effectivity Unit The number of the effectivity unit involved in this transaction. You can define effectivity units in the Effectivity Units (tcuef0502m000) session. Specification If this check box is selected, a specification is present. Initial Hidden Pos. Dependent on the order type, LN displays the number of the order line. Planned Supply The number of plan items that you expect to receive according to the planned order(s). The number of items is displayed either:
You can change the planned orders for which a number of items is displayed in the current field. Note LN retrieves the planned supply data from the Items - Planning session. Scheduled Receipts The number of items that you expect to receive according to the orders that are transferred to the execution level. Transferred orders are, for example: The number of items is displayed either:
You cannot change the transferred orders in Enterprise Planning. Note LN retrieves the scheduled receipt data from the Planned Inventory Transactions (whinp1500m000) session. Receiving Site Receiving Item The receiving plan item. Warehouse The warehouse in which the items are received, or from which the items are issued. Business Partner The ship-from business partner. If no ship-from business partner is known, the buy-from business partner is displayed instead. Supplying Site The supplying site. Note This field always contains a value. In case of planned production order or planned purchase order the value is set to the current company. Supplying Item The supplying plan item. Ordered Date Ordered Quantity The quantity of item ordered. Order Confirm Date The date on which the order is confirmed. Confirmed Quantity The total confirmed quantity of the item ordered. Allocated to BP If this record involves a supply, this field indicates the sold-to business partner to which this supply was allocated or demand pegged. If this record involves a demand, this field indicates the sold-to business partner to which the supply that can fill this demand must have been allocated or demand pegged. LN uses this characteristic to match supply and demand. Allocated to Business Object If this record involves a supply, this field indicates the order, or order line, to which the inventory was allocated or the supply object was demand pegged, such as, Sales Order, or Service Order. If this record involves a demand, this field indicates the order, or order line, to which the supply that can fill this demand must have been allocated or demand pegged. LN uses this characteristic to match supply and demand. Note The following fields are always used in combination; together, they identify the relevant order or order line:
Allocated to Reference If this record involves a supply, this field indicates the reference code to which the inventory was allocated or the supply object was demand pegged. If this record involves a demand, this field indicates the reference code to which the supply that can fill this demand must have been allocated or demand pegged.
Use Unallocated Inventory If this check box is selected, unallocated inventory may be used to supply demand. Enterprise Planning uses allocated inventory first. If there is not enough allocated inventory, Enterprise Planning also uses unallocated inventory. If this check box is cleared, Enterprise Planning can use only allocated inventory to fill the demand. Option List ID Project Peg Origin The origin of the project peg for the planned production order. Allowed values Planning Group Contains Customer Furnished Materials If this check box is selected, the item order line contains customer furnished materials ether in the form of materials directly supplied by the customer or subassemblies containing materials supplied by the customer. Note The indicator is visible when the Customer Furnished Materials check box is selected Implemented Software Components (tccom0100s000). Is Customer Furnished Material If this check box is selected, the item order fully consists of customer furnished materials. Note The indicator is visible when the Customer Furnished Materials check box is selected Implemented Software Components (tccom0100s000). Demand Initial Hidden Allocated to Business Object Type If this record involves a supply, this field indicates the type of order to which the inventory was allocated or the supply object was demand pegged, such as, Sales Order, or Service Order. If this record involves a demand, this field indicates the type of order to which the supply that can fill this demand must have been allocated or demand pegged. Note
Planning Group Supply Unit Effectivity Number The number of the effectivity unit involved in this transaction. Note You can define effectivity units in the Effectivity Units (tcuef0502m000) session. Initial Hidden Allocated to Business Object Type If this record involves a supply, this field indicates the type of order to which the inventory was allocated or the supply object was demand pegged, such as, Sales Order, or Service Order. If this record involves a demand, this field indicates the type of order to which the supply that can fill this demand must have been allocated or demand pegged. Note
Confirmed Demand Confirmed Demand The confirmed demand for the plan item expressed in the number of items. Ordered Date The date on which the order is created. Planned Available (Confirmed) View the amount of the planned available inventory that has been confirmed. Initial Hidden Distribution Line The number of the distribution line the order belongs to. Effectivity Unit Allocated to Business Object Type If this record involves a supply, this field indicates the type of order to which the inventory was allocated or the supply object was demand pegged, such as, Sales Order, or Service Order. If this record involves a demand, this field indicates the type of order to which the supply that can fill this demand must have been allocated or demand pegged. Note
Update Click this button to let LN carry out an update, when you entered additional demand or additional supply in the Simulate field. Initialize, Roll, and Update Scenario Start the Initialize, Roll, and Update Scenario (cprpd4200m000) session. Change Company Start the Change Company (cpcom1200s000) session. Consume Forecast Carries out forecast consumption. Copy Planned Orders to Scenario Start the Copy Planned Orders to Scenarios (cprrp1240m000) session. Confirm Order Planning Start the Confirm Planned Orders (cprrp1200m000) session. Transfer Order Planning Start the Transfer Planned Orders (cppat1210m000) session. Update Planned Order Assignment Start the Update Planned Order Assignment (cprrp1260m000) session to update the buyer or planner code on a selection of planned orders. General Item Details Starts the Items - General (tcibd0501m000) session. Item Ordering Details Starts the Item - Ordering (tcibd2100s000) session. Item Buy-from-BPs Starts the Item - Purchase Business Partner (tdipu0110m000) session. Item Planning Details Starts the Items - Planning session. Resource Master Plan Click this button to zoom to the Capacity Use by Planned Order (cprrp2100m000) session in which you can get a period-based overview of the required capacity of a specific resource, or to the Resource Master Plan (cprmp3501m000) session in which you can analyze the capacity planning of a specific resource. Specification Displays the selected record's specification. Line Details If the Order Type and Order Number are present on the selected order line, the detail session for this order starts. If the Order Type and Order Number are cleared, a new item order plan session is started. The new session starts in detail mode beginning with the orders on the start date of the period selected for the line. Note: The second Item Order Plan (cprrp0520m000) session is not synchronized with the original session. Quarantine Inventory Start the Quarantine Inventory (whwmd2171m000) session. Include Derived Items Click this button to switch from (Item only) to (Item + derived items) or vice versa.
| |||