Setup example for cost peg transfer rules

Planning groupProjectElementActivityInheritTransfer InInheritTransfer Out
AWithin GroupAcross Groups

 

Transfers to project pegs related to planning group A are allowed if the transfers originate from projects within the same planning group. Transfers out from these project pegs to project pegs related to projects across all planning groups of the company are allowed.

Planning groupProjectElementActivityInheritTransfer InInheritTransfer Out
AWithin GroupAcross Groups
AA1XWithin GroupWithin Project

 

For project A1, which belongs to planning group A, the rules for transfers to the project are inherited from the planning group. Transfers out of project A1 are now restricted to cost pegs within the project. To all other projects belonging to planning group A, the general rules set for planning group A still apply.

Planning groupProjectElementActivityInheritTransfer InInheritTransfer Out
AWithin GroupAcross Groups
AA1XWithin GroupWithin Project
AA1E1ACT1Not AllowedNot Allowed
E2ACT2Not AllowedXWithin Project
BWithin ProjectWithin Project

 

For cost account A/A1/E1/ACT1, no cost peg transfers in or out are allowed. Transfers to cost account A/A1/E2/ACT2 are not allowed, but transfers out are allowed to cost pegs within project A. The transfer-out rules are inherited from the transfer-out rules set for project A.