Generate Inventory Commitment (whinp2200m000)Use this session to generate inventory commitments of (unblocked) inventory for orders of type Issue that are not yet fully committed. When you generate inventory commitment, LN commits the required inventory to a specific order line. As a result, the available inventory for other orders or other order lines is decreased. To generate commitments:
The quantity to be committed depends on the order origin and is calculated as follows:
Note To commit inventory manually, use the Inventory Commitments (whinp2100m000) session.
Order Origin The origin of the order. Commitment according to shipping constraints. If this check box is selected, the commitment for sales
order will be according to the shipment constraints. Cancel Inventory Commitment for Complete Orders Not Fully Committed. If this check box is selected, any inventory commitment
is cancelled for complete orders that are not fully committed. The complete
order is a shipment constraint. Only Sales Orders with commitment as procedure step. If this check box is selected, only sales orders with
sales order types that have the Generate Inventory Commitment (whinp2200m000) session as a procedural step, are taken
into account. 1. Lists the priority of the origin of the orders used when
generating commitments. One is the highest priority, and eight is the lowest
priority. Order by Planned Delivery Date If this check box is selected, within the order
priorities specified using the Order Priority fields, the orders are prioritized by planned
delivery date. The orders with the oldest planned delivery date are committed
first. If this check box is cleared, within the order priorities specified using the Order Priority fields, the orders are prioritized by order number. The orders with the lowest order number are committed first.
| |||||||||||