Release Plan (tsspc3240m000)

Use this session to release an existing group planning. You can release a complete group planning or select the groups and activities that must be released.

 

Selection Range
Activity Origin
The origin of the activity. The activity origin can be service order, work order or planned activities.

Allowed values

Activity Origin

Level
The group planning level to be released.

Allowed values

Level

Group
The From and To fields define a range of: groups that must be released.
Group
The From and To fields define a range of: groups that must be released.
Activity Set Sequence
The From and To fields define a range of: activity sets in a group that must be released.
Activity Set Sequence
The From and To fields define a range of: activity sets in a group that must be released.
Planned Start Time
The From and To fields define a range of: planned start time of the activities that must be released.
Planned Start Time
The From and To fields define a range of: planned start time of the activities that must be released.
Planned Finish Time
The From and To fields define a range of: planned finish time of the activities that must be released.
Planned Finish Time
The From and To fields define a range of: planned finish time of the activities that must be released.
Options
Simulate
If this check box is selected, LN runs the release process in simulation mode. The results are not saved in the database. This process enables you to review the results before releasing the selected groups and activities.
Keep Existing Assignments for Service Orders
If this check box is selected, LN does not overwrite the existing assignments for service orders.
Note

This field is enabled only when the Activity Origin field is set to Service Order.

Only Release when Group has an Allocated Resource
If this check box is selected, LN releases the group planning only if the group has allocated resources.
Delete Released Groups
If this check box is selected, LN deletes the selected groups after the release process.
Delete Released Activity Sets
If this check box is selected, LN deletes the selected activity sets after the release process.
Delete Released Activities
If this check box is selected, LN deletes the released activities after the release process.
Print Options
Process Report
If this check box is selected, LN generates process report. The report contains details of all activities that are released.
Error Report
If this check box is selected, LN generates error report. This report contains details of all warnings and errors that occurred during the release process.