Planned Activity - Other Requirements (tsspc2112m000)

Use this session to view and maintain any extra requirements (other than labor or materials) required to carry out a planned activity.

If you manually add an activity in the Planned Activities (tsspc2100m000) session, LN asks if you want to list its extra requirements in this session.

If you delete a planned activity from the Planned Activities (tsspc2100m000) session, its extra requirements are automatically deleted from this session.

 

Planned Activity Number
The number that identifies serialized item for the planned activities.
Note

LN generates the planned activity number based on the data specified in Number Group for Planned Activities and Series for Planned Activities fields in Service Planning and Concepts Parameters (tsspc0100m000) session.

Activity Line Number
The line number that distinguishes one Planned Activity from another for the same Planned Activity Number.
Note

LN generates the planned activity line number based on the data specified in Number Group for Planned Activities, Series for Planned Activities and Step Size for Activity in Service Planning and Concepts Parameters (tsspc0100m000) session.

Installation Group
A set of serialized items that have the same location and are owned by the same business partner. Grouping serialized items into an Installation group enables you to maintain them collectively.
Installation Group
The description of the Installation group.
Activity
The (code of the) activity for which the requirements are listed.
Description
The name or description of the activity.
Activity Status
The status of the activity.
Line
The number used to distinguish each requirement listed for the planned activity.
Cost Type
The cost type of the extra requirement.
Item
The item specified as cost or service. If you select an item, the Description field is disabled.

Miscellaneous costs such as administrative cost, hotel stay, telephone bills and so on are maintained as the Cost items or Service items. To register the cost, use the browse arrow to select the item from the Items - General (tcibd0501m000) session.

Important!

To represent the miscellaneous cost, you can define an item of type Service or Cost in the Items - General (tcibd0501m000) session.

Description
The description of the item. Enter the description if you do not select any value in the Item field.
Cost Component
The cost component used to categorize the costs of the planned activity's extra requirements.
Cost Component
The name or description of the cost component.
Quantity
The quantity of the other requirement line that is required to carry out the reference activity. The default value for the field is one. You can change the value.
Note

If you cannot define the quantity and the unit of a cost type, set the quantity to zero (0).

Quantity (Unit)
The unit in which quantity is measured.
Cost Price
The Cost price is retrieved from the Items - Costing (ticpr0107m000) session.
Cost Price (Currency)
The currency of the cost price.
/
The unit for which the cost price is given.
Cost Amount
The cost amount is calculated using the following e formula.
Cost Amount= Quantity x Cost Price

This is a display field.