Field Change Orders (tssoc5100m000)

Use this session to create, view, and maintain field change orders (FCOs).

 

FCO
The number that identifies the field change order (FCO).

When you create an FCO in the details session, you select a series to assign the FCO to, and LN generates the number for the FCO.

Description
A brief description of the field change order (FCO).
Order Date
The date on which you create the field change order.
FCO Status
The field change order's (FCO) status.
Item
The item that you create the field change order (FCO) for.
Note

You can only maintain this field if the FCO's status is Free.

Description
The description or name of the code.
No. 1
The activity carried out as part of the feld change order.
No. 1
The name or description of the activity.
No. 2
A second activity to be carried out as part of the field change order.
No. 3
A third activity to be carried out as part of the field change order.
No. 4
A fourth activity to be carried out as part of the field change order.
No. 5
The fifth activity to be carried out as part of the field change order.
Service Department
The (code of the) service department that carries out the activities listed for the field change order.
Description
The name of the service department.
Earliest Start Date
The earliest date that the field change order can start.
Note

This value must be greater than or equal to the order date.

Latest Finish Date
The date by which the field change order must be finished.
Note

This value must be greater than or equal to the Earliest Start Date.

Buy-from BP
If you subcontract out the field change order (FCO), this is the (code of the) buy-from business partner responsible for carrying out the FCO.
Service/Cost Item
The service item code, or cost item code that you use to itemize the subcontracted field change order work.

 

Print Field Change Orders
Prints the field change orders.