Planned PRP Purchase Order (Material) (tppss6110m000)

Use this session to maintain planned purchase orders related to material.

Note

Use the Maps section to view the location of the Ship-to Address. You must select only one record at a time.

Click the Get Initial Time button if you want to reset order dates.

Note

Initially, the planned order date and the planned delivery date are set based on the control budget and the lead time. The planned delivery time is determined in this way:

  • If the control budget is of type Activity, the planned delivery time generated from the activity budget line.
  • If the control budget is of type Element, the planned delivery time is generated from the element.
  • If the requirement is caused by an extension and the extension date is later, the extension date becomes the planned delivery time.
  • If no start date is found, the project planned delivery time is used.
  • If a generated planned order time occurs in the past, it is changed to the current date. This will also shift the planned delivery time.

 

Project
The code that uniquely identifies the project.
The current project status. The current project status. This status must be Free or Active, for all PRP orders in this session.
Planned Purchase Order
The code that uniquely identifies the purchase-order for planned PRP materials.

If you create a new order, this field displays the chosen order series. If you save the PRP order, the first free number of the series is automatically allocated.

Planned Order
Material Order
Item
The code that uniquely identifies the item.

The code consists of a project code field and an item code field

If the first segment is filled, the item is a project-specific cost object. If it is clear, the item is a standard cost object.

Description
The description of the series.
Quantity
The ordered quantity of the item.
Note
  • Quantity cannot be negative.
  • Quantity is rounded off, according to the rounding factor of its unit (as defined in the Units (tcmcs0101m000) session).
  • The minimum order quantity is specified in the Item - Ordering (tcibd2100s000) session, but you can overrule this.
  • The maximum order quantity is specified in the Item - Ordering (tcibd2100s000) session, but you can overrule this.
  • The order-quantity increment is specified in the Item - Ordering (tcibd2100s000) session, but you can overrule this.
Unit
The unit of measure in which the quantity is expressed.
Project Warehouse
The warehouse to which the ordered materials are delivered.
Note

If you leave this field empty, the materials are delivered directly to the project.

Ship-to Address
The ship-to code and description.
Order Status
The current order's status. This shows the extent to which the order has been processed.
Cost Control
Element
The code that uniquely identifies the element to which the cost object of this order belongs.
Activity
The code that uniquely identifies the activity to which the cost object of this order belongs.
Extension
The code that uniquely identifies the contract extension to which the cost object of this order belongs.
Cost Component
The code that uniquely identifies the cost component of the cost object of this order.
Order Text
If this check box is selected, a text is present.
Specification
Dates
Planned Order Time
The planned date and time to order the purchase.

Click Calculate, to calculate the planned order time derived from the planned delivery time minus the order lead-times that are defined in Procurement.

Planned Delivery Time
The date and time when you plan to receive the materials. Click Calculate to calculate the date and time from the budget data.
Note

All planned orders are generated based on the control budget. The delivery date of the planned order is determined in this way:

  • If the control budget is of type Activity, the start date of the activity budget line is used
  • If the control budget is of type Element, the start date of the element is used
  • If the requirement is caused by an extension and the extension date is later, the extension start date is used
  • If no start date is found, the project start date is used
  • If a generated date occurs in the past, it is changed to the current date.
Effectivity Unit
The effectivity unit code. This is a display field.
Description
The description or name of the code.
Transaction Time
The transaction date and time for the planned purchase order.
Business Partners
Request for Quotation
If this check box is selected, LN creates a request-for-quotation (RFQ), instead of a purchase order, when the approved PRP Purchase Orders are transferred.
Buy-from Business Partner
The code that uniquely identifies the buy-from business partner.

If you leave this field empty and you transfer the PRP purchase order, LN creates a request for quotation (instead of a purchase order).

Buy-from BP Description
The business partner's name.
Ship-from Business Partner
The code that uniquely identifies the ship-from-business-partner.
Planning
Buyer
The code that uniquely identifies the buyer.
Note

LN defaults the value when the planned PRP orders are generated, using the Generate Planned PRP Orders (tppss6200m000) session.

The name of the employee. The employee can be a buyer or a planner.
Planner
The code that uniquely identifies the planner.
Note

LN defaults the value when the planned PRP orders are generated, using the Generate Planned PRP Orders (tppss6200m000) session.

Purchase
Purchase Office
The purchase office that purchases materials according to transferred PRP purchase orders.
Purchase Unit
The unit in which you purchase an item, also referred to as the purchase quantity unit.
Purchase Type
The default purchase type. You can change the value or leave this field empty.
Lot Selection
Lot
A number of items produced and stored together that are identified by a (lot) code. Lots identify goods.
Pricing
Pricing
Purchase Contract
The purchase contract (defined in Procurement) according to which the item is purchased.
Contract Line
The position number of the purchase contract to which the planned purchase order is related.
Currency
The contract currency.
Purchase Price
Click Calculate Purchase Price to calculate the purchase price.

This is determined by the information in the Pricing module under Common. You can retrieve prices from the price matrices.

Currency
Purchase price currency of the planned purchase order.
Discount
The discount that is granted on the planned purchase order.
Amount
The total price of the planned purchase order.

 

Calculate Purchase Price
Calculates the purchase price of the planned purchase order.