Check Customized Item Completed (tppss2203m000)

Use this session to check whether the production order of a customized item (linked to a milestone) has been reported as completed. If it has been reported as completed, the milestone has been reached.

 

Project
The From and To fields define a range of: projects.
Plan
The code that uniquely identifies the plan.
Milestone
The From and To fields define a range of: milestones. Enter the milestones related to the customized item on which you want feedback.
-
The From and To fields define a range of: milestones. Enter the milestones related to the customized item on which you want feedback.

 

Project Selection
Starts the Project Selection (tppdm6800m000) session that allows you to select a range of projects based on the defined criteria.