| Type of ActivityWBS Element A type of activity usually used to break down the project scope
into smaller pieces. You can define work for a work-break-down structure
element. You can aggregate the costs from control accounts or work packages.
You cannot book costs on this activity type. Control Account The only type of activity that can be linked to an organization
breakdown structure. At this level functional responsibility for work and costs
can be assigned. You can detail short-span jobs in project cost accounts and
use it for the execution of a project. Planning Package Planning packages are identified during planning to time phase
major activities within a project cost account. You cannot book costs on this
activity type. Work Package A type of activity. You can detail short-span jobs in work
packages and use it for the execution of a project. Milestone An activity of zero days that usually represents a significant
event in the project. In many cases the completion of a phase of major
deliverable. Milestones can be used for the moment of invoicing and the
calculation of earned value.
| |