Publish Project Data (tpbod0200m000)Use this session to publish LN Project data to Infor ION for transfer to other software applications. The following Project data can be published:
Usually, you publish data from this session once. However, if errors occur during the publication process or if other software applications need a new set of data, you can rerun this session. Note
Size The number of records that must be simulated. If you enter a value of 100, the first 100 records that fall within the selection criteria must be simulated. Default value The default value is zero, which means all records that fall within the selection range are simulated. Company The company range for which the data must be
published. Use Verb Specify what is published. Allowed values Logical ID(s) Show BODs do not use ION routes and are sent directly to other
applications. Use this field to specify the logical ID(s) of the receiving
application. Logging If this check box is selected, published BODs are logged. Output Specify the log output. Allowed values Single XML-file per BOD If this check box is selected, a separate log file is
generated for each published BOD. If this check box is cleared, one log file is generated with the xml of all published BODs. Note This check box is only available if the Output is BOD. Location The server or client to which the output files must be
written. Directory The directory on the server or client to which the output files
must be written. ProjectMaster ProjectMaster If this check box is selected, projects with their activity structure are published. LaborCostMaster Standard If this check box is selected, standard labor cost objects are published. Project If this check box is selected, project-specific labor cost objects are published. SundryCostMaster Standard If this check box is selected, standard cost objects relating to sundry costs are published. Project If this check box is selected, project-specific cost objects relating to sundry costs are published. ProjectBalance ProjectBalance If this check box is selected, cost control by activity is published. ProjectPeriodBalance ProjectCosts ProjectCosts If this check box is selected, project costs are
published. ProjectExtension ProjectExtension If this check box is selected, extensions are published. ProjectBid ProjectBid If this check box is selected, bids are
published. ProjectEstimate ProjectEstimate If this check box is selected, estimates are
published ProjectRevenue ProjectRevenue If this check box is selected, installments are published. ProjectBudget ProjectBudget If this check box is selected, project budgets are published. ProjectProgress ProjectProgress If this check box is selected, project activity
progress is published. Progress is retrieved from the Activity Physical Progress (tpppc1560m000) session.
| |||