Generate Network Planning (tipcs4210m000)

Use this session to generate network planning by project in which the following is determined:

  • The planned start and finish dates of activities.
  • The rough capacity requirements for each activity.
  • The planned start and completion dates of the projects.
  • In case of a main project the planned start and finish dates of the sub-project activities.

Related topics

 

Project
A collection of manufacturing and purchasing actions that are performed especially for a particular customer order. A project is initiated by a customer order for items having a To Order order policy. The purpose of a project is to plan and coordinate the production of these items.

For a standard-to-order production, the project is only used to link the item with the customer order. Otherwise, a project can include:

  • Customized item data (BOMs and routings)
  • Project planning (activity planning)

A budget is a special type of project. A budget is used to plan and estimate, not to carry out production.

 

Continue
Executes the process that you set up in this session.