| To set up operation with Customer Furnished MaterialsThis topic describes how to set up your system to support the
execution of operations with customer furnished materials. The transfer of
components and subassemblies is supported. Setup Step 1. Implemented software componentsConsider the following check boxes in the Implemented Software Components (tccom0500m000) details session: Customer Furnished Materials If you want to support the flow of subassemblies and
components during the subcontracting process, you must select the Customer Furnished Materials check box. Demand Pegging Demand pegging is required to identify subassemblies
uniquely. If the Demand Pegging check box is selected, every
subassembly is allocated to a specific production order by means of a reference number. Note: It is not possible to use Customer Furnished Materials with Project Pegging implemented.
Step 2. Item data for item and subassemblies with customer furnished
materialsSubassemblies In the Items - General (tcibd0501m000) details session, define two items for which the Subassembly check box is selected. These items
represent respectively the subassembly sent by the manufacturer to
the subcontractor, and the subassembly sent back by the subcontractor after
work is done. The item type of the subassembly you send back to the
manufacturer must be Manufactured. If the manufacturer sends only material, you just need
to define an item code for the subassembly created by the
subcontractor. Define the following data for the
subassemblies: Warehouse In the Items - Ordering (tcibd2500m000) session, find the defined subassemblies. For the
subassembly that you receive from the manufacturer, enter in the Warehouse field the warehouse in which you receive
the subassembly. For the subassembly that you send back to the manufacturer,
enter the warehouse from which you send the subassembly. Cost price To generate an effective cost component structure,
define the assemblies' costing data in the Items - Costing (ticpr0107m000) session. Calculate and actualize the cost price in the Calculate Cost and Valuation Prices (ticpr2210m000) session while the Actualize Standard Cost and Valuation Prices check
box is selected. Price For the item that is sent back by the subcontractor,
you must determine the price the manufacturer pays to the
subcontractor.
Step 3. Terms and conditionsDefine terms and conditions in the following
cases: - If components are shipped by sales orders.
- If the the manufacturer is responsible for the components'
planning.
For more information about agreements, refer to Setting up terms and conditions. Step 4. Purchase contractIf components are planned by the subcontractor or shipped by
sales order, define a contract in the Purchase Contracts (tdpur3100m000) session. The Buy-from Business Partner field must contain the
manufacturer's code. Use the Terms and Conditions ID field to link the applicable
terms and conditions agreement. Define the rest of the contract in the Purchase Contract Lines (tdpur3101m000) session. Step 5. User profile purchaseDefine your user profile in Sales Control so that LN can generate and
handle sales orders properly. Step 6. Work center and shop floor warehouseIn the Work Centers (tirou0101m000) session, define the work centers as a work center for
regular production orders. Do not select work center type Subcontracting Work Center. Link the following information to the subcontracting work
center: - In the Shop Floor Warehouse field, you can enter a shop floor warehouse. This warehouse is used to monitor
the subassemblies' and components' inventory levels.
In the Shop Floor Control Parameters (tisfc0500m000) session, select the Use of Shop Floor Warehouses check box. Step 7. RoutingIn the Routing Operations (tirou1102m000) session, link the defined subassemblies, warehouses,
and work centers. Link to the first subcontracted
operation: The subassembly which represents the product that the
manufacturer sends to the subcontractor. It is recommended that the subassembly
warehouse equals the BOM warehouse of the materials sent to the
subcontractor. Link to the other subcontracted
operations: The applicable work center. Link to the last subcontracted
operation: The subassembly which represents the product that you send
back to the manufacturer. The warehouse in which you receive the subassembly
takes a default value from the Warehouse field in the Items - Ordering (tcibd2500m000) session.
Step 8. BOMOptionally, in the Bill of Material (tibom1110m000) session, enter the operation number for which the
subcontractor requires the material in the Operation field. | |