Operation subcontracting without material flow supportThe simplest way of subcontracting in LN is to create a subcontracting purchase order to record the operations that are outsourced to a subcontractor. This means that you purchase labour from a subcontractor. For this type of subcontracting, no material is supplied to the subcontractor. To start a subcontracting process without material supply, you must set up the following data:
Step 1. Release production order Create and release a production order for the item with subcontracted operations. On the item's routing, subcontracting work centers are defined. Step 2. Generate subcontracting purchase order In the Generate Subcontracting Purchase Orders (tisfc2250m000) session, generate a subcontracting purchase order. The number of the subcontracting purchase order is displayed on the subcontracted operation in the production planning. If more than one operation is subcontracted, with more than one subcontractor involved, a purchase order is generated for every subcontractor. Step 3. Handle purchase order Handle the purchase order according to the defined purchase order procedure. For more information, refer to Flexible purchase order processing and Overview of purchase order handling. Step 4. Handle warehouse order Carry out the warehouse order procedure. For more information, refer to To handle warehousing orders. Step 5. Complete operations Complete the subcontracted operations, and, if applicable, further operations. Step 6. Process purchase invoice Process the purchase invoice. For more information, refer to Processing purchase invoices. Step 7. Close production order Close the production order. Ad hoc subcontracting If you had not planned to subcontract one or more operations, and consequently no subcontracting work centers are defined in the routing, use the Subcontract Operations (tisfc2210m000) session to replace an existing work center with a subcontracting work center on the operations that you want to subcontract.
| |||